DATA CENTER COST 2026: DATA DICTIONARY Publisher: Metro Colo Advisory, https://metrocoloadvisory.com/data-center-cost/ Data as of: October 24, 2026. License: CC BY 4.0. FILE 1: data-center-cost-figures.csv One row per published figure on the Data Center Cost 2026 page. figure_id: stable ID (DCC-001 and up). IDs are kept across updates. category: Build, Lease, Run, AI hardware, Build vs lease, Connectivity, Market or Timelines. metric: what the figure measures. value: the figure as published, in words. value_low / value_high: numeric value, or the low and high ends of a range, in the unit shown. unit: unit for value_low and value_high. geography: market the figure covers. period: date or period the figure describes. source_name / source_url: the published source. Two URLs are separated by a space. mca_calculation: "yes" if the figure is Metro Colo Advisory arithmetic on the cited sources (method in notes), "no" if published by the source as shown. notes: method, caveats and related figures. data_as_of: date the row was last checked. FILE 2: data-center-power-cost-by-pue.csv Annual electricity cost to run 1 MW of IT load around the clock at different PUE levels. pue: power usage effectiveness (facility power divided by IT power). it_load_mwh_per_year: 1 MW x 8,760 hours. facility_mwh_per_year: IT load times PUE. price_usd_per_mwh: US average industrial electricity price, June 2026 (EIA, 9.17 cents per kWh). annual_cost_usd: facility MWh times price. MCA calculation. FILE 3: data-center-construction-cost-per-watt.csv Construction cost per watt of IT capacity by market, Turner & Townsend Data Centre Construction Cost Index 2026-27. usd_per_watt_low / usd_per_watt_high: same value when a single figure is published. Construction only; excludes land and site costs, which the Cushman & Wakefield all-in figure includes. FILE 4: data-center-lease-rate-change-by-size.csv Change in average asking rates by requirement size, first half of 2026, CBRE. asking_rate_change_percent: percent change in H1 2026. LIMITS Published averages and ranges, not quotes. Real projects and leases vary widely by market, density, term and timing. GPU and hardware prices move quickly; check the period column. All-in development cost (Cushman & Wakefield) and construction-only cost (Turner & Townsend) measure different things and should not be compared directly.