Independent advisory for colocation, GPU and data center projects

A reply within one business day

Powered Land for Data Centers Prices, Interconnection, Substations and Behind-the-Meter Power

Recent Northern Virginia data center land deals ran $3.5 million to $6.3 million an acre, against about $125,000 for ordinary land in Loudoun County. Most "powered" listings overstate their power. We assess what a site can actually serve, and when, and lay out the economics of selling, leasing or building on it.

Assess My Site
For landowners, developers and investors One site or a full portfolio A reply within 24 hours

Engagements start at $45,000. Portfolio reviews are usually six figures.

Powered land is land with an electrical supply a data center can actually use: a utility commitment, or on-site generation, for a defined number of megawatts by a defined date, close enough to transmission that the connection is buildable. It is the scarcest input in data center development, and it is priced accordingly. In the first quarter of 2026, data center land accounted for 30 percent of all development site spending in the US, up from 19 percent a year earlier, and entitled, power-ready parcels in the tightest submarkets now trade at many times the price of ordinary land.

The word "powered" is doing a lot of work in most listings, though. A site next to a transmission line, a site with a load letter, a site with a completed utility study and a site with a signed facilities agreement are four very different assets. What a data center buyer pays for is the last one, and the gap between them is measured in years and in millions of dollars. Whether you have data center land for sale, are weighing a data center land acquisition that needs data center due diligence, or hold a utility will serve letter and want to know how far it moves the numbers before a data center valuation, the answer starts with where the site sits on the power ladder below.

SHARE OF LAND SPENDING
30%
of all US development site spending went to data center land in Q1 2026, up from 19% (Avison Young)
NORTHERN VIRGINIA
$3.5M to $6.3M
per acre in closed 2025 and 2026 data center land deals (NAHB, county records)
TIME TO POWER
4+ years
median from interconnection request to operation, double the early-2000s figure (Berkeley Lab)
TRANSFORMERS
60 to 120 weeks
from order to delivery for utility-grade units in 2026; longer for 100 MVA and up

When to bring in an advisor

A site assessment is the usual first engagement of our data center consulting practice.

Scope My Site Assessment
  • You hold land with a utility letter and want to know whether a data center buyer will treat it as power.
  • A developer has made an offer, and you want the economics behind it laid out before you answer.
  • You are deciding whether to sell the land, lease it or develop it yourself.
  • You are developing a portfolio of powered sites and need a go-to-market strategy: which buyers fit each site, how to present it, and which sites to lead with. See assessing a portfolio of powered sites.
Data center land prices: what power does to an acre
Price per acre, Northern Virginia unless noted
Countywide median, Loudoun, 2025ordinary land
$125K
Amazon, Ashburn, 2026122 acres for $427M
~$3.5M
Starwood, Fairfax County, 202642 acres for $166.8M, a county record
~$4M
Twin Creeks, Leesburg, Nov 202597 acres for $615M
~$6.3M
Pending transactions, NoVA and Northeastsites with large power access
$8M+

Prices checked October 2026. Sources: NAHB, July 2026, for the county median and the Amazon and Starwood transactions; Data Center Knowledge, October 2026, citing Loudoun County records, for Twin Creeks; CBRE, February 2026, for pending transactions above $8 million per acre. Northern Virginia is the extreme; secondary markets price far lower, but the pattern is the same. Free to cite with a link to this page.

Outside Northern Virginia, prices run far lower: across 232 recorded closed sales since 2024, the median is about $184,000 an acre. See every deal, with the deed or filing behind it, in our Powered Land Deal Tracker.

Own or control a site that might serve a data center?
Send the location, acreage, zoning, and whatever you have on power: utility correspondence, study results, distance to transmission. A reply within 24 hours, with a first read on what the site can realistically serve and which buyers it fits.
Assess My Site

What Makes Land "Powered": The Power Ladder

Every site sits somewhere on this ladder. Value, and the pool of buyers, rise sharply at each rung. The most common mistake in the market is pricing a site at a rung it has not reached.

  1. Often marketed as “powered” (steps 1 to 3)

    Rung 1: Near transmission

    What existsA line or substation nearby; nothing requested from the utility
    For a buyerAn option, not a site. Proximity is necessary but proves nothing about capacity
  2. Often marketed as “powered” (steps 1 to 3)

    Rung 2: Load request filed

    What existsAn application to the utility for a stated number of megawatts; a queue position
    For a buyerA place in line. Queues are long and often oversubscribed; a position is not power
  3. Often marketed as “powered” (steps 1 to 3)

    Rung 3: Will-serve or load letter

    What existsA utility letter indicating it can serve the load, usually conditional and often without a date
    For a buyerMeaningful but soft; read the conditions. Many letters promise study, not delivery
  4. Can be underwritten (step 4)

    Rung 4: Study complete

    What existsSystem impact and facilities studies done, with the upgrades, cost and timeline identified
    For a buyerNow the site can be underwritten: the capacity, the cost to connect and the energization date are known
  5. Where buyers pay the premium (steps 5 and 6)

    Rung 5: Agreement signed

    What existsAn electric service or facilities agreement, with deposits or collateral posted and a date
    For a buyerPowered land in the sense buyers pay for. Most of the premium attaches here
  6. Where buyers pay the premium (steps 5 and 6)

    Rung 6: Energized

    What existsThe substation built and power available at the fence
    For a buyerThe top of the market; a building can start and tenants can lease against a real date
Less certain powerPower at the fence
WHAT THAT MEANS
A seller with a rung-two site who prices it like a rung-five site does not sell, and a buyer who pays rung-five money for rung two carries years of risk. The first job of a site assessment is to place the site on this ladder from the documents, not the listing, and to price what it would take to climb.

Will Serve Letters: What They Promise and What They Do Not

A will serve letter is a letter from a utility stating that it is able and willing to provide service to a property, subject to conditions. Utilities issue them for water, sewer and gas as well as electricity, and for ordinary development they are routine. For a data center, the electric will serve letter is where many sites stop, and where many listings overstate their position. Read three things in it: the capacity (a stated number of megawatts, or only "service"), the date (a firm energization date, or none), and the conditions (usually completed studies, upgrades paid for by the customer, a signed service agreement and collateral). A letter that promises to study the load, with no megawatts and no date, is rung three at best. A letter tied to a completed facilities study with a date is worth far more. Buyers and lenders will read it the same way, so it is better to read it that way first.

Generation Interconnection Is Not Load Service

Solar and storage developers often hold a generation interconnection: permission to send power onto the grid at a stated point. A data center needs load service: permission to draw power from the grid, around the clock. They are different requests, studied separately, in different queues, and load service is usually handled by the local utility, backed by a load study or will serve letter and later an electric service agreement. A site can hold a large generation position and still be years from serving a data center.

QuestionGeneration interconnectionLoad service
What it permitsSending a stated number of megawatts onto the gridDrawing a stated number of megawatts from the grid, 24 hours a day
Who studies itUsually the grid operator or transmission provider, in a generation queueUsually the local utility, in its large-load process
What proves itA generation interconnection agreementA load study or will serve letter, then an electric service agreement
WHAT BUYERS ASK TO SEE
The load request and its queue position; the load study or will serve letter, with the megawatts, the date and the conditions; the draft or signed electric service agreement and the tariff it falls under; and, where the site also holds a generation position, whether the utility has said anything in writing about serving load at the same substation. A generation agreement on its own answers none of those questions.

Is This Land Actually Powered? The Six Stages to Check

Land is powered when the utility has signed an electric service agreement for a stated number of megawatts and will set a meter on a schedule. A load request, a will-serve letter or a finished study is real progress, but none of them obliges the utility to deliver power by a date.

The power ladder above shows where a site sits. This section is the paperwork behind it: what each utility document proves, what it leaves open, what utilities that publish their terms charge for it, and where you can check it without taking the seller's word. Before you price a site, our data center due diligence team can read the utility file for you.

  1. Capacity inquiry

    Load letter or large load service request
    What it proves

    The utility has a request on file for a stated load at this parcel, usually with a site plan and a ramp schedule. Dominion takes these through its Data Center Portal.

    What it does not

    Capacity. One Texas cooperative's request form says submitting it "does not guarantee electric service and does not reserve system capacity," and it sets no place in line.

    What it costs

    Consumers Energy in Michigan collects a $100,000 deposit to develop a proposal, and its first evaluation "may take up to 6 months."

    Where to check it

    Ask for the utility's written acknowledgment with the date and megawatts. New York's grid operator posts its interconnection queue, which covers "generation, transmission, and load facilities," as a monthly spreadsheet. ERCOT publishes counts only, and PJM's new Large Load Registry will post "only aggregated data."

    Sources: Texas electric cooperative, Large Load Electric Service Request form; Consumers Energy, Our Data Center Process; Dominion Energy, Data Center Requests; NYISO, Interconnections; ERCOT, Batch Zero Update (Sept 11, 2026); PJM, Large Load (FERC Docket ER26-3515-000).

  2. Will-serve letter

    A letter from the utility
    What it proves

    The utility serves the territory and could serve the property. The letter usually lists next steps and the fees or land rights that may follow.

    What it does not

    Service. Salt River Project in Arizona says it plainly: "Will serve letters do not guarantee service, only that SRP could serve the property." Dominion lists the letter outside its main steps: one "can also be provided, if required."

    What it costs

    Little time. SRP asks for five to 10 business days to process a request, far too fast to include a capacity study. Dominion's engineering phase alone typically takes 9 to 12 months.

    Where to check it

    Will-serve letters are not filed in public records. Ask for the letter itself on utility letterhead and check that it names the parcel, a megawatt figure and a date. SRP also reserves the right to modify a letter after it is issued.

    Sources: SRP, Will Serve letter process; Dominion Energy, Data Center Requests; Dominion Energy, load forecast documentation filed with PJM (Jan 6, 2026).

  3. Load or facilities study

    Study report; an Engineering Letter of Authorization (ELOA) at Dominion
    What it proves

    The utility has modeled the load at this point on the grid and named the upgrades, the cost and the time to connect. This is the first stage a buyer can underwrite.

    What it does not

    A reservation. Dominion does not count engineering-stage load as firm, and the customer is not obliged to go further. Studies also run in rounds: AEP Ohio's latest began October 1, 2026, so a missed window means waiting for the next one.

    What it costs

    AEP Ohio: $10,000 to $100,000 per study by size, paid within 45 days, with a target of 45 days to finish, or 60 if regional transmission upgrades are needed. Texas: a flat $100,000 study fee for large loads. Dominion: a $250,000 ELOA deposit, and the engineering phase "typically takes 9 to 12 months."

    Where to check it

    Ask for the study report. Dominion reports the megawatts at each stage to PJM, and nearly three times as much load sits at the engineering stage as under signed service agreements (chart below). The totals carry no site names, so they show the odds, not your parcel.

    Sources: AEP Ohio, Data Center Tariff; Utility Dive, Texas PUC adopts softened rules on data center interconnection (Sept 21, 2026); Dominion Energy, documentation filed with PJM (Jan 6, 2026).

  4. Construction agreement

    Construction Letter of Authorization (CLOA) at Dominion; Letter of Agreement at AEP Ohio
    What it proves

    The customer has put money at risk and the utility is ordering equipment and building. Dominion counts load at this stage as firm.

    What it does not

    A meter or a fixed date. If the project stops, the customer carries the cost of what the utility has already built.

    What it costs

    Dominion: if the customer cancels before energization, "the customer must reimburse the Company for any investments made on its behalf." Long-lead equipment deposits are due before Dominion orders and are refunded at energization. AEP Ohio: the customer repays "100% of the buildout costs" if it cancels the project or delays it by more than 12 months.

    Where to check it

    Ask for the signed agreement and proof of the deposits. In Georgia, the utility "must provide the PSC all new contracts with data centers at least 30 days before execution."

    Sources: Dominion Energy, documentation filed with PJM (Jan 6, 2026); AEP Ohio, Data Center Tariff; Georgia PSC, Data Center Fact Sheet (Dec 1, 2025).

  5. Electric service agreement

    ESA: the contract that sets capacity, collateral and the meter
    What it proves

    This is the commitment buyers pay for. Dominion needs a signed ESA "in order to set a meter and provide electric service," and the ESA sets the contracted capacity and collateral.

    What it does not

    A guaranteed date. Even AEP Ohio's ESA includes only "a good faith estimate of the energization date of service."

    What it costs

    AEP Ohio gives customers 60 days to sign the Letter of Agreement and ESA or lose their place. Customers without the required credit ratings post collateral "equal to 50% of the total minimum charges for the full term of the contract," and surety bonds are not accepted.

    Where to check it

    Large single-customer agreements sometimes go to the state commission. Arizona's commission approved TEP's 286 MW Project Blue agreement on December 3, 2025, in docket E-01933A-25-0187. Most ESAs under a standard tariff are never filed, so a missing docket proves nothing either way.

    Sources: Dominion Energy, documentation filed with PJM (Jan 6, 2026); AEP Ohio, Data Center Tariff; Arizona Corporation Commission news release (Dec 9, 2025).

  6. Ramp schedule

    The ramp exhibit in the ESA or the utility tariff
    What it proves

    How fast the contracted megawatts become usable and billable once power is on. At AEP Ohio the ramp lasts no more than four years, with contract capacity of at least:

    What it does not

    That the full load is there on day one. A buyer modeling rent from the full contracted figure in year one is ahead of the schedule.

    Where to check it

    Read the ramp exhibit in the ESA and the utility's tariff. AEP Ohio publishes its ramp on its data center tariff page.

    Source: AEP Ohio, Data Center Tariff.

  7. Energized

    Meter set, power at the fence, ramp under way

    This is the finish line. Dominion says loads under 50 MW "typically require 1-2 years to complete," while larger loads "will most likely require the extension of transmission lines and the construction of a new substation." Check it with the utility's in-service confirmation. Georgia Power files a quarterly large load report with its commission that tracks project stage and in-service dates, with customer names redacted.

    Sources: Dominion Energy, Data Center Requests; Georgia Power quarterly large load report, Georgia PSC Dockets 56002 and 55378.

How much Dominion load sits at each stageData center contracts in Dominion's Virginia zone as of July 2026, in megawatts. Only the construction and service agreement stages count as firm.
Engineering (ELOA)Study stage, not firm
32,473 MW
Construction (CLOA)Firm, utility building
9,356 MW
Service agreement (ESA)Firm, meter can be set
11,997 MW
Not firmFirm, under constructionFirm, signed ESA

Source: Dominion Energy zone submission, PJM Load Analysis Subcommittee (Sept 29, 2026). Ratio of engineering-stage to ESA megawatts is our calculation (32,473 / 11,997 = 2.7).

Red flags in powered land listings

Each row pairs what a listing claims with the document that would prove it.

Generator interconnection rights sold as load service

The listing says

"Interconnection approved" or "grid position secured" on a solar, battery or gas generation site.

Ask for instead

A load study and a service agreement for the data center load itself. FERC's December 18, 2025 order for PJM says co-located load tied to the grid "must procure one of the new transmission services." Injection and offtake capacity "can be very different at the same substation."

Sources: Foley & Lardner on the FERC PJM co-location order (Dec 2025); LandGate, a land data vendor (Aug 26, 2026).

A solar or battery site marketed as data center power

The listing says

"Operating solar farm with a live interconnection, ready for a data center."

Ask for instead

Evidence the utility has studied the new load. In Texas, the operating 180 MW Oberon Solar site still needed Oncor to perform "necessary interconnection studies for the requested load addition" and amend its interconnection agreement before adding about 110 MW of load, now expected in May 2028.

Source: New Project Media (July 14, 2026).

Promised dates that slip

The listing says

"Power next year," based on an early utility letter or a conversation with the utility.

Ask for instead

The date in a signed agreement and the order status of long-lead equipment. Utilities now "routinely push back the delivery timelines promised in these initial power agreements." Google says utilities in many markets are "telling us four or five, sometimes ten years to interconnect."

Sources: Bisnow (Aug 25, 2024); Network World (Jan 15, 2026).

No named utility agreement

The listing says

"Megawatts available" or "power secured," with no utility, document or date named.

Ask for instead

The document's name (study, ELOA, CLOA, Letter of Agreement or ESA), the utility that signed it, the megawatts, the date, and the deposits or collateral posted. If the seller cannot name one, the site is at stage one or two.

Why a signed agreement still takes years

Even after the paper is signed, the utility has to buy and install equipment with multi-year lead times.

Power transformers
128 weeks
Average lead time in Q2 2025, about two and a half years from order.
Generator step-up transformers
143 weeks
Average lead time in Q2 2025, the units that connect generation to the grid.
Dominion, order to energization
About 3 years
Long-lead equipment deposits are refunded at energization, "typically 3 years after the point of order."

Sources: Wood Mackenzie, Mind the gap: tackling supply-chain challenges in the electric T&D sector (Oct 15, 2025); Dominion Energy, documentation filed with PJM (Jan 6, 2026). 128 weeks / 52 = 2.5 years is our calculation.

Requested, signed or running?

Our AI Power Reality Check sorts each utility's data center load into the same three buckets. When a seller quotes a megawatt figure, ask which one it is.

Requested

Stages 1 to 5: the utility's full pipeline, from a filed load request through signed agreements. Much of it is still at the request or study stage.

Signed

Stage 5: load under a signed electric service agreement, with collateral posted and a ramp schedule attached.

Running

Energized load that is drawing power today. This is the only figure a tenant can lease against now.

Buying or selling land sold as powered? Send us the utility documents.

We read the will-serve letter, studies and agreements and tell you which stage the site is really at. You'll hear back within 24 hours. For larger reviews, see our data center consulting.

Send the Utility Documents

Check Your County: Local Votes, Power Prices and Utility Load

Pick a state and county to see the data center votes and moratoriums on our list there, what industrial power costs in that state, and which of its utilities report data center load requests on our AI Power Reality Check.

The votes come from county and city agendas, public notices and local news, and update here as we add them. A county with nothing listed has no vote on our list yet, which is not the same as nothing scheduled.

Choose a state to start. You can then narrow it to one county.

Sources: our local data center votes list, U.S. Energy Information Administration statewide industrial prices on our data center electric rates page, and the AI Power Reality Check utility scoreboard.

Looking at land for a data center? Send us the parcel and the utility.

We check the power path, the local votes and the utility's large-load rules, and tell you what stands between the land and a signed service agreement. You'll hear back within 24 hours.

Request a Site Review

Data Center Power Requirements

How much power a data center needs depends on how many racks it holds and how dense they are, plus the power used to cool and support them. The utility request, and the land, are sized from that. Our guide to data center power consumption works through the math, and data center power infrastructure shows the equipment between the utility and the racks.

WorkloadPower per rackWhat it means for a site
Enterprise and cloudAbout 5 to 15 kWAir-cooled halls. Illustrative: a 10 MW building at the meter, at a PUE of about 1.4, has about 7 MW of IT load, roughly 700 racks at 10 kW
High densityAbout 30 to 60 kWLiquid-assisted cooling; more power in less floor area
Rack-scale AIAbout 120 to 140 kW for a GB300 NVL72, more for the next generationDirect-to-chip liquid cooling, heavy floor loads, and power per square foot several times an enterprise building

The utility sees more than the IT load. Cooling, power conversion and lighting add overhead, measured as PUE (power usage effectiveness): at a PUE of 1.3, a facility with 50 MW of IT load draws about 65 MW from the grid, and it is the grid figure that the utility request, the substation and the tariff are sized to. Campuses are now commonly planned at 100 MW and up, and a single hyperscale campus can reach several hundred megawatts. That is why the power a site can secure, rather than its acreage, usually sets how much data center it can hold. See data center cost for what each megawatt costs to build.

Large-Load Interconnection: What Utilities Require Now

Utilities used to connect large customers on standard terms. Since 2025, most of those serving data center demand have adopted large-load tariffs that shift the cost and risk of new capacity onto the customer: long minimum terms, minimum payments whether or not the power is used, collateral, and exit fees. They change the economics of a site, and they are why a load letter alone no longer means much.

Utility or stateThresholdKey terms
Dominion Energy, VirginiaGS-5 rate class25 MW and up, from January 1, 202714-year minimum contract; pay at least 85 percent of contracted transmission and distribution capacity and 60 percent of generation demand regardless of use; collateral of about $1.5 million per MW; four-year ramp
AEP OhioData Center Tariff25 MW and upPay at least 85 percent of contracted demand; 12-year minimum; exit fee of 36 months of minimum charges. After it was approved, AEP's large-load forecast fell by half
Texas, ERCOTSenate Bill 675 MW and upInterconnection standards with study fees, financial security, curtailment and remote-disconnect requirements. The PUCT adopted its rules in September 2026, after the governor ordered a pause in August on new data center grid interconnections while the state audits the ERCOT queue
Georgia PowerOver 100 MWLarge loads pay for upstream grid infrastructure; developers must show end-user commitments and post collateral.
ElsewhereCommonly 20 to 75 MWSimilar tariffs filed or approved across dozens of utilities; 44 of 77 large-load filings reviewed by CoBank include added collateral requirements

Sources: CoBank DELTa database, April 2026; Berkeley Lab, August 2026; Columbia Law School, June 2026; Greenberg Traurig on Texas SB 6; Utility Dive, September 2026, on the adopted Texas rules. Tariffs are changing quickly; confirm current terms with the utility.

WHAT THAT MEANS FOR LAND
A tariff with a 14-year take-or-pay and $1.5 million per MW of collateral turns a power commitment into a financial commitment only a creditworthy user can make. For a landowner, the practical buyer pool is the developers and operators who can post that collateral, and the site is worth most to them when the study work is done and the path to energization is clear.

The Data Center Substation

As an engineering rule of thumb, a data center above roughly 10 to 20 MW usually needs its own substation, fed from the utility's transmission or sub-transmission system and stepping down to the medium voltage the campus distributes. Large campuses connect at 138 kV or 230 kV, typically with two independent feeds. That is a different number from the tariff thresholds in the table above, which run from 20 MW to over 100 MW: one is about equipment, the other about contract terms. The substation, not the building, is almost always the longest item in the schedule.

What it costs

Core substation equipment typically runs $3 million to $7 million; a 69 kV substation of the kind common in suburban and rural areas, $6 million to $15 million. The full utility interconnection, including transmission lines, easements and utility charges, can run $20 million to more than $100 million depending on distance and voltage. Transformer prices have risen 40 to 55 percent since 2022.

How long it takes

Utility-grade transformers run 60 to 120 weeks from order; units of 100 MVA and up, 90 to 130 weeks or more. Switchgear runs 40 to 65 weeks. Developers who deliver on time order long-lead equipment during site control, before final design.

Who builds and pays

Either the utility builds it and charges the customer, or the developer builds and owns it, common above about 20 MW. Either way, the cost and the dates belong in the land underwriting, and a planned substation site on the parcel adds value.

Sources: TrueLook, July 2026; Buildermuse, June 2026; Build, April 2026; ATK Energy, May 2026.

Behind-the-Meter Power for Data Centers

Behind-the-meter power, also called behind the meter generation, is generation on the customer's side of the utility meter: gas turbines, reciprocating engines, fuel cells, batteries, or a data center built next to an existing power plant. It exists because the grid cannot deliver on the timeline developers need. More than 130 GW of generation has been proposed to serve planned data center projects in the US, over 80 percent of it gas. For a landowner, gas supply on or near the site has become a value driver in its own right. For how these sources work alongside grid service, see how data centers are powered.

TechnologyTime to deployCostWhere it fits
Fuel cellsAs little as about 90 days for modular unitsHighest capital cost, about $3,000 to $4,000 per kWBridging power fast, sites with air permit constraints, phased campuses
Reciprocating engines and aeroderivative turbinesMonths to about two years, subject to equipment supplyPower at about $106 to $107 per MWh, against about $86 for average industrial grid powerBridging to grid power, or primary power at sites with pipeline gas
Heavy-duty and combined-cycle gasThree to seven yearsAbout $101 per MWh for combined cycleLarge campuses with long horizons and firm gas supply
Co-location at a power plantDepends on the plant and regulatorsNegotiated with the plant ownerLand next to existing generation; regulatory treatment is still being settled, and at least one high-profile arrangement had to be restructured after FERC rejected it

Sources: Rabobank, September 2026, and Rabobank, June 2026, for the pipeline, deployment times and cost per MWh; SemiAnalysis, April 2026, for fuel cell capital cost.

WHAT THAT MEANS
Behind-the-meter generation buys speed at a premium, roughly a quarter more per MWh than grid power, plus air permits, fuel contracts and a power plant to run. On a 50 MW campus running at 80 percent load, that premium works out to about $7 million a year, or roughly $42 million over a six-year bridge (MCA calculation). For most sites it is a bridge to grid power. Some campuses, though, are designed to run islanded from day one on solar, battery storage and on-site firm generation, and buyers diligence those harder, as set out below. Either way, a site with both a gas lateral and a credible utility path is worth more than one with either alone.

Solar, Storage and Fuel-Cell Campuses: How Buyers Test Them

A campus built to run on its own power, with solar, batteries and fuel cells or engines and no grid connection at the start, can work. It is also the configuration buyers and lenders test hardest, because there is no utility behind it on the worst day. These are the questions their teams work through. The numbers are illustrative, not drawn from any site.

AN ILLUSTRATIVE WINTER DAY What carries the load when the sun is low
Clear winter dayBattery starts the day empty0265212 am6 am12 pm6 pm12 amFacility load, 52 MWMW
Third overcast dayLittle sun, nothing stored0265212 am6 am12 pm6 pm12 amFacility load, 52 MWMW
Solar Battery Firm generation (fuel cells or engines)

On a clear winter day the sun refills only about 250 of the 400 MWh of storage, and the battery is empty by about 9 p.m. On an overcast day there is almost nothing to store, and firm generation carries nearly the whole load. That is why buyers size firm generation to the full load on its own, with one unit spare.

Illustrative only: 40 MW of IT at a PUE of 1.3 (52 MW at the meter), solar peaking at 110 MW on a clear winter day, 400 MWh of storage. Not drawn from any site.

The eight questions buyers' teams work through

THE POWER MATH
1

Annual energy is not hourly supply

A solar array's annual output says little about any given hour. A data center draws close to full load at night, in winter and through a week of overcast skies, so buyers model supply hour by hour, not year by year.

2

Size from the meter, not the IT load

Facility load is IT load times PUE. Illustrative: 40 MW of IT at a PUE of 1.3 is about 52 MW at the meter, around the clock.

3

Battery hours at full load

Divide stored energy by facility load. Illustrative: 400 MWh against 52 MW is about 7.7 hours nominal, before losses and reserves. That covers nights, not a run of cloudy winter days.

4

Firm generation for the worst hour

Buyers check that the fuel cells, engines or turbines can carry the full load in the worst hour on their own, at net dependable output rather than nameplate, with at least one unit spare (N+1). This is a point for your engineer to confirm.

THE DOCUMENTS BEHIND IT
5

Fuel logistics, and whether supply is contracted

When permanent fuel supply arrives, how the site runs until then, how much fuel is held on site, and whether supply and transport are under contract or only planned.

6

Air permits for on-site generation

Whether the permits cover continuous operation at the planned output, not only backup use, and what limits they set on hours and emissions.

7

Delivery dates, acceptance tests and remedies

Equipment delivery dates in the supply contracts, ready-for-service (RFS) acceptance tests that prove output before handover, and liquidated damages if dates slip.

8

A later grid tie

A path to a utility connection later, even years out, adds resilience and widens the pool of buyers and lenders.

PLANNING A CAMPUS LIKE THIS?
Our site and portfolio reviews for owners and developers test it the way a buyer's team and its lenders will, against all eight questions, with engineering points flagged for your engineer to confirm.
Not sure where your site sits on the ladder?
Send what the utility has told you, in writing if you have it. We read the letters and studies the way a data center buyer's team will, and tell you what the site can serve, when, and what it would take to move it up a rung.
Send My Power Documents
What we see in practice
The most common gap we see: a site described as powered on the strength of a utility indication that is not under contract, or a will-serve letter that promises less than it appears to. Buyers price the contracted megawatts and the date they arrive, so that is where every assessment starts.

What Data Center Buyers Look for in a Site

Power comes first, but a site that fails any of the rest does not sell to a data center buyer at a data center price. The full criteria for choosing between sites are on the data center site selection guide; these are the ones that decide whether land qualifies at all.

FactorWhat buyers checkWhy it matters
PowerCommitted megawatts, energization date, voltage, redundant feeds, the tariff and its collateralSets what can be built, when, and at what carrying cost
Acreage and shapeEnough contiguous, buildable land for the building, substation, generators, cooling and setbacks, with room to phaseAbout 0.5 to 1 acre per megawatt, so a 100 MW campus needs roughly 50 to 100 acres; odd shapes and easements cut usable area. See data center land requirements
Zoning and entitlementData center use by right or by special exception, height, noise and generator rules, and the local political temperatureLocal opposition and moratoriums now stall projects as often as power does
FiberDistance to long-haul routes, diverse paths, carriers on or near the siteFiber is cheaper to extend than power, but distance and diversity still cost time and money
Water and coolingWater supply and discharge if the design uses it; climate for free coolingSome counties restrict water use; closed-loop designs reduce the need
Physical riskFlood zone, seismic, wind and wildfire exposure; soil and slopeInsurers, lenders and tenants all price it
GasPipeline or lateral access for behind-the-meter generationIncreasingly a value driver on its own
IncentivesState sales tax exemptions and local abatements, and their current legislative statusSeveral states are revisiting incentives; confirm before relying on one

Selling Land to a Data Center Developer: Land Acquisition and Deal Structures

Data center land acquisition has become one of the most active corners of commercial real estate: developers, operators and hyperscalers are buying sites years ahead of need, and data center land sales made up nearly a third of development site spending in early 2026. For a landowner, the structure of the deal matters as much as the price.

Outright sale

The simplest structure and the most common. Price depends on the power rung, the entitlements and the buyer pool; expect contingencies tied to power and zoning, and long diligence periods.

Option to purchase

The developer pays for the right to buy within a period while it works the power and permits. Lower risk for the buyer, some income and upside for the owner, and the land is tied up while it runs.

Ground lease

Long-term income while keeping ownership; common where owners do not want to sell or taxes favor it. Terms, rent resets and reversion rights matter more than the headline rent.

Joint venture

The owner contributes land, sometimes with power work already done, for an interest in the project. Highest potential upside, and the most need for independent advice on the development economics.

Data center land for sale: how sites actually trade

Most data center land for sale never appears on a public listing. Powered sites trade mainly off-market: through the land teams at the large real estate firms, through direct approaches from developers and operators, and through utilities and economic development agencies that keep lists of qualified sites. Listings that do advertise "powered land for sale" or "data center ready land" often describe proximity to transmission rather than committed capacity, so the power documents matter more than the listing. Our work for owners is the assessment, and it comes first and stands on its own: what the site is, from the documents, which buyers it fits, and the economics of each path, with stated assumptions for your appraiser or broker. Representation on a sale or lease is a separate, later engagement, run with a licensed broker where the state requires one.

Where landowners leave value on the table

1

Selling before the power work is done

The largest jumps in value come at the study and agreement rungs. An owner who can afford to take the site up the ladder often captures much of that premium instead of the buyer.

2

Talking to one buyer

Developers, operators and hyperscalers value the same site differently. A single unsolicited offer is rarely the market.

3

Long options on cheap terms

An option that ties up the land for years at a low fee, with extensions, can leave the owner holding the risk and the buyer holding the upside.

4

Ignoring the community

Neighbors, noise and water now decide approvals. A site with a plan for them is worth more than one that has not considered them.

WHAT YOU RECEIVEWhat a powered land assessment puts on your desk
Power position, from the documentsWhere the site sits on the power ladder, read from the utility's own letters, studies and agreements, not the listing.
What the site can serveMegawatts, energization date, voltage and redundancy, and the campus size the acreage can hold.
Tariff and interconnection termsThe large-load tariff, collateral, minimum terms, substation cost and timeline that come with the power.
Economics by pathHow the site's economics change by rung and by path, set against current market land deals, with stated assumptions for your appraiser or broker.
Sale, option, lease or ventureWhich structure fits your goals and taxes, and the terms to hold out for in an option or sale agreement.
Buyer fitWhich kinds of buyers the site suits, from colocation operators to AI and GPU clouds, and what each will ask for in diligence.
A written report and the model behind it, every finding sourced Follow-up questions from you and your advisers answered in writing Questions on delivered work answered without the clock running
WHAT A SITE ASSESSMENT COSTS Fixed fee, agreed in writing before any work starts.

Engagements start at $45,000. Portfolio reviews are usually six figures. Every engagement is scoped to the sites, so the fee is set once we know what has to be verified on power, approvals and economics.

A written assessment, with the timeline fixed in the scope Paid by you, never by a buyer or developer

Assessing a Portfolio of Powered Sites

An owner or developer with several powered sites, from a few megawatts to roughly 100 MW per campus, has a different problem from a single landowner: which sites to lead with, what to fix first, and which path suits each one. We position sites for the buyers below hyperscale, which in our experience is the largest set of active buyers for sites this size: colocation and wholesale operators, enterprise users, AI compute companies, GPU clouds and neoclouds, regional and edge operators, and developers. We also run capacity searches for AI, GPU and enterprise buyers, so we see what they ask for, what they screen out and what they pay, and we test each site against that.

Triage

Which sites to lead with, which to hold, and which are not data center sites, ranked on power position, timing and buyer fit.

Readiness gaps, ranked

The gaps a buyer's team will find on each site, ranked by what each costs to close against what it does for buyer interest and timing.

The path for each site

Sale, ground lease, powered shell, build to suit or joint venture, site by site, with the economics of each and the assumptions stated.

One-page site summary

For each top site: power, date, acreage, zoning, fiber and the open items, in the form a buyer's team screens on.

Buyer diligence pack

The questions buyers' engineers and lenders will ask, your answer to each with the document behind it, and the open gaps ranked by risk, so diligence starts from a complete file rather than a request list.

Holding more than one site?
Send the list, with what you have on power for each. Portfolio work is scoped separately; see site and portfolio reviews for owners and developers.
Scope My Portfolio Review

How We Help

We run this as a fixed-fee engagement for owners, developers and investors, from a single site to a multi-site portfolio, paid by the client. The work is a written site assessment: where the site sits on the power ladder, what it can realistically serve and when, the utility and tariff terms that will apply, the substation and interconnection cost and timeline, behind-the-meter options if the grid is slow, which buyers and tenants it realistically fits, and the economics of each path. It is the usual first engagement of our data center consulting practice, typically part of a feasibility study. When the answer is to build, we advise on build to suit and powered shell structures. Representation on a sale or lease, if you want it later, is a separate engagement. For buyers and lenders, the same work runs as data center due diligence.

Frequently Asked Questions

What is powered land?

Land with an electrical supply a data center can use: a utility commitment or on-site generation for a defined number of megawatts by a defined date, with a buildable connection to transmission. The strongest form has a signed electric service or facilities agreement; proximity to a power line alone does not make land powered.

How much do data centers pay for land?

It depends on the power position, the market and the entitlements. In Northern Virginia, closed data center land deals in 2025 and 2026 ran about $3.5 million to $6.3 million an acre, against a Loudoun County median of about $125,000. Avison Young puts entitled land without power there at about $4 million an acre and powered land at $6 million and up. Elsewhere, JLL has put powered land at $200,000 to $1 million an acre, and Avison Young has said land in lower-cost markets that might sell for about $10,000 an acre without a power path can be worth six figures an acre once one is established.

How do I know if my land is suitable for a data center?

Start with power: how many megawatts the utility can deliver, when, and on what terms. Then acreage and shape, zoning and local attitudes, fiber, water, flood and seismic risk, and gas access. A written site assessment places the site on the power ladder from the utility's own documents and identifies the kinds of buyers it fits.

What is a data center substation?

A dedicated electrical facility that takes high-voltage power from the utility's transmission or sub-transmission system and steps it down to the medium voltage a data center distributes. As a rule of thumb, facilities above roughly 10 to 20 MW need one, a separate question from the size at which large-load tariffs apply; large campuses connect at 138 kV or 230 kV with two independent feeds.

How much does a data center substation cost?

Core equipment typically runs $3 million to $7 million, and a 69 kV substation $6 million to $15 million. The full interconnection, including transmission lines, easements and utility charges, can run $20 million to more than $100 million depending on distance and voltage. Transformers take 60 to 120 weeks or more to arrive.

What is behind-the-meter power?

Electricity generated on the customer's side of the utility meter: gas turbines, reciprocating engines, fuel cells, batteries, or a data center built next to an existing power plant. Data centers use it when the grid cannot deliver on their timeline, usually as a bridge to utility power, though some campuses are designed to run islanded on their own generation from day one.

How much does behind-the-meter generation cost?

On-site gas engines and aeroderivative turbines produce power at roughly $106 to $107 per MWh and combined-cycle plants at about $101, against about $86 for average industrial grid power. Fuel cells deploy fastest but carry the highest capital cost, about $3,000 to $4,000 per kW. The premium is the price of speed.

Can a solar and battery campus serve a data center around the clock?

Only with firm generation behind it. Annual solar output is not hourly supply, and batteries sized for several hours of full load cover nights, not a run of cloudy winter days. A campus designed to run islanded needs on-site generation, such as fuel cells, engines or turbines, that carries the full load in the worst hour with a spare unit, plus contracted fuel, air permits for continuous operation, and equipment delivery dates backed by acceptance tests and liquidated damages. Buyers and lenders diligence these campuses harder, and a later grid tie adds resilience.

What is large-load interconnection?

The process of connecting a very large customer, typically 20 to 75 MW and up depending on the utility, to the grid. It now usually involves studies, deposits, collateral and a large-load tariff with long minimum terms and minimum payments. Dominion's GS-5, for example, applies from 25 MW with a 14-year minimum and about $1.5 million per MW in collateral.

How long does it take to get power to a data center site?

Commonly several years. Berkeley Lab found the median time from interconnection request to operation has doubled to more than four years, and constrained markets run longer. Transformer lead times alone are 60 to 120 weeks or more.

Should I sell my land to a data center developer or lease it?

It depends on your timeline, taxes and appetite for risk. Outright sale is simplest; an option pays you while the developer works the power; a ground lease keeps ownership and provides income; a joint venture offers the most upside and the most risk. Whatever the structure, value rises sharply as the power work advances, and one unsolicited offer is rarely the market.

How much land does a data center need?

About half an acre to one acre per megawatt as a planning rule, so a 100 MW campus needs roughly 50 to 100 acres and a gigawatt campus several hundred. Power, not acreage, usually sets how big a site can go. Our data center land requirements guide covers acreage, zoning and permitting in full.

What is a will serve letter?

A letter from a utility stating it is able and willing to serve a property, subject to conditions. For a data center, read the capacity, the date and the conditions: a letter with no megawatts and no date usually promises study, not delivery, while one tied to a completed facilities study and an energization date is worth far more to a buyer.

Is a generation interconnection the same as power for a data center?

No. A generation interconnection, which solar and storage developers often hold, is permission to send power onto the grid. A data center needs load service, permission to draw power around the clock, which is a different request, study and queue, usually with the local utility, backed by a load study or will serve letter and later an electric service agreement. A site can hold a large generation position and still be years from serving a data center.

What are data center power requirements?

They depend on rack count and density plus overhead. Enterprise racks draw about 5 to 15 kW, high-density racks 30 to 60 kW, and rack-scale AI systems about 120 to 140 kW each. Cooling and power conversion add overhead measured as PUE: at 1.3, 50 MW of IT load draws about 65 MW from the grid, which is the figure the utility request is sized to. New campuses are commonly planned at 100 MW and up.

What is a data center power purchase agreement?

A long-term contract to buy electricity, often from a specific generator such as a wind, solar, gas or nuclear plant, at an agreed price. Data centers use them to fix power costs and meet clean energy goals; they sit alongside the utility service agreement rather than replacing the physical connection, unless the generator is co-located behind the meter.

What is the difference between powered land and a powered shell?

Powered land is the site with its power position. A powered shell is a building on powered land, with the power and core infrastructure delivered and the interior fit-out left to the tenant. See our powered shell guide for how those deals are structured.

Do you sell or market powered land for owners?

Not as part of our consulting. The assessment comes first and stands on its own: a fixed-fee, written review of what the site can serve and when, which buyers it fits, and the economics of each path, with stated assumptions for your appraiser or broker, for one site or a portfolio. Representation on a sale or lease is a separate, later engagement, run with a licensed broker where the state requires one.

Assess Your Site

Send the location, acreage, zoning, and everything you have on power: utility letters, study results, the distance to transmission and gas. A reply within 24 hours, with a first read on where the site sits and whether it is worth assessing in full. If it is not a data center site, we say so before you spend anything.

The price is set before the sale.
Where a site sits on the power ladder, and how well its power position is documented, decide its price more than the acreage does.
Assess My Site

The site: data center land requirements for acreage, zoning and permitting, and the data center developers who buy and build.

The numbers: data center cost, data center valuation and data center financing.