Data Center Due Diligence
What to Verify Before You Buy, Finance or Lease a Data Center, and What Usually Goes Wrong
Most data center deals fail on points the offering memorandum treats as settled: power promised but not contracted, a building tenants cannot use, a lease that looks better than it pays. We run independent diligence for a fixed fee, with no stake in the outcome.
Scope a Diligence ReviewFixed fee, paid by the client. No operator or tenant pays us on a diligence assignment.
Data center due diligence, often called technical due diligence, is the independent check an investor, lender or acquirer runs before committing capital: whether the power is contracted or only promised, whether the building suits the tenants the plan assumes, whether the leases pay what the rent roll shows, and whether the market will still want the facility in five years. A data center's value is set by power and density, not square footage, and those are the two easiest things to overstate.
Most deals that go wrong fail on points the offering memorandum treats as settled. Diligence is the core of our data center consulting practice: a fixed fee, paid by the client, with no stake in whether the deal closes. We design nothing and operate nothing, and no operator or tenant pays us on a diligence assignment.
When to Bring in an Advisor
Four situations call for an independent review before you commit:
Megawatts in the memorandum
The offering memorandum states megawatts, but it is not clear how much is contracted and how much is only a utility indication.
Tenants the building may not support
The plan assumes tenants the building may not physically serve, such as AI deployments at 100 kW per rack or more.
An older operating facility
You are buying an older operating facility and need to know what equipment, density and site conditions will cost after closing.
A deadline before the answers
You are entering exclusivity or facing a bid deadline before the power, building and market questions are answered.
What Actually Sets a Data Center's Timeline
Construction is rarely the long pole. The utility and the equipment queue are, so a model that starts the clock at groundbreaking understates the schedule.
The Seven Areas of Data Center Due Diligence
A complete review covers seven areas. The first two decide most deals. The last two are where problems tend to surface after closing.
Decides most deals
- A utility agreement stating capacity, dates and cost
- Transformer and switchgear orders with delivery dates
- Utility capacity separated from usable IT load in the numbers
Decides most deals
- Floor loading in pounds per square foot, from the structural drawings
- Clear height
- Cooling design and how far the loop reaches
- Generator and UPS topology as built, not as a tier label
- Every lease read for escalators, power basis, renewals, expansion rights and termination
- Tenant credit and concentration
- What happens at each expiry
- Vacancy, absorption and preleasing data
- Competing projects with contracted power
- The model's rate tested against current quotes
- Zoning as written for the parcel
- Whether a city or a county controls it
- Any pending moratorium or ordinance
- The noise, water and traffic conditions that prompt opposition
Where problems surface after closing
- Fiber on poles or underground
- Diverse entry points
- The meet-me room
- The cost of a circuit to the nearest interconnection hub
Where problems surface after closing
- Certifications checked against the issuing registry, not the brochure
- Maintenance and incident records
- Staffing
- PUE as measured, not as designed
What it costs to get each area wrong is on our data center cost page. The lease terms behind area three are in the data center lease guide, and how to read a tier claim is in data center tiers.
What You Receive: A Diligence Memo Written for Your Investment Committee
The deliverable is a written memo your committee can act on. It covers six things:
Every model assumption, marked
Each assumption is marked verified, unverified or contradicted, with the supporting document cited.
Power position, papered
Contracted, energized and sought capacity separated; utility capacity converted to IT load; every equipment date checked against an order.
Lease-by-lease read
Escalators, power basis, renewals, expansion rights and delivery obligations, read in every lease and reconciled to the rent roll.
Building fit
Floor loading, cooling and electrical design set against the tenants the plan assumes.
Market and rate test
The model's rates against current signings in that market, and against competing supply that has contracted power.
Open items, ranked
What could not be verified, ranked by the cost of being wrong, so the committee knows what to make a condition of the deal.
20 MW of utility capacityCONTRADICTED
The executed agreement covers 4 MW. The other 16 MW is a study request with no date.
Anchor lease escalator at 3% fixedVERIFIED
Lease section 4.2 and the second amendment. Matches the rent roll.
Transformer delivery in Q3 2027UNVERIFIED
No purchase order produced. Requested from the seller, and a closing condition until it is.
Fixed fee, paid by the client. Engagements start at $45,000. Multi-site and portfolio work is scoped separately and commonly runs into six figures.
Power: The Question That Decides Most Deals
Every offering memorandum shows a power figure. The question is what stands behind it. Three tiers recur across our work, and they separate a marketable building from a plan.
Contracted and energized
A signed utility agreement, transformers installed, capacity available now.
Available but not contracted
The utility has said the capacity exists, often at a nearby substation, but nothing is signed and no equipment is ordered.
Being sought
A study is underway or planned. Utility studies take one to two years, and the transformer that follows takes more than three (lead times on our data center cost page).
Two checks on any power figure
Utility capacity is not IT load, and rated power is not deliverable power. A "24 MW campus" may have 4 MW energized and 20 MW still in the queue, so the phasing matters more than the total.
Utility Capacity Is Not IT Load
Take a single 7.5 MVA utility service. After transformer losses, power distribution and cooling at a typical PUE, it supports roughly 5 MW of IT load. A plan built on the 7.5 MVA figure overstates what can be leased: about a third of the headline never reaches the racks.
The Building: Which Tenants It Can Physically Serve
The specification decides the tenant market. Three items decide most of it, and each has a document that settles it.
| Specification | What it decides | Where to find it |
|---|---|---|
| Floor loading | Whether rack-scale AI is possible at all. A fully populated rack-scale cabinet weighs about 1,400 kg, and many industrial slabs are specified well below what a hall of them needs. | The general notes on the structural sheets, in pounds per square foot. Concrete compressive strength in PSI is a different number. |
| Cooling design and reach | The density ceiling. Air cooling with containment handles about 35 kW per rack, rear-door heat exchangers about 70 kW, and direct-to-chip cooling serves rack-scale systems. Whether a chilled water plant exists decides whether liquid cooling is a fit-out or a rebuild. | The mechanical drawings and site plan, plus the water temperature and flow the plant can deliver at the rack. |
| Electrical topology | The building's real redundancy, and so which tier claims survive a tenant's questions. "Tier 3 design" and "Tier III certified" are different claims. Data center tiers explains the difference, and the provider comparison covers how the major operators approach certification. | The one-line diagram, checked against the marketing. |
A hall drawn for far more cabinets than its power can serve. Layouts at 4 to 5 kW per cabinet look full on paper but cannot serve the tenants in the plan. The same power can support fewer cabinets at 10 to 30 kW, or a few dozen rack-scale systems, and the cooling and slab limits decide which. The build to suit and powered shell guides cover how those choices are made before the slab is poured.
Tenants, Leases and the Rent Roll
The rent roll is a summary. The value is in the leases, so each one is read for the terms that move revenue over its remaining life. Our data center lease guide covers each clause from the tenant's side, which is the side a buyer inherits.
Escalators may be fixed, tied to CPI or capped, and rent may be billed on connected, committed or metered power. Two leases at the same headline rate can differ in value by about a fifth over ten years.
Renewals at then-current rates favor the owner; capped renewals do not. Expansion rights promised to tenants can quietly commit capacity the model still counts as available.
When each lease ends, what the market rate is likely to be at that point, and how much of the revenue depends on one or two tenants.
Owners may owe tenants dates and remedies for space not yet built. Missed dates can trigger abatement or termination rights, and the buyer inherits them.
Who stands behind each lease, especially when the tenant is a newer AI or GPU operator. Operators now ask this before they ask about price, and buyers should too.
What the owner has promised on availability and remote hands, and how many service credits it has already paid out.
Market, Entitlement and the Rest
Market and demand
Vacancy of 1.4 percent and 80 percent preleasing are national averages. The test is the specific market: which developers are building with contracted power, what they are quoting, and whether the model's rate is one tenants are actually signing.
Current figures are in our market guides for Northern Virginia, Dallas, Atlanta, Chicago and the New York metro. Rate structure is on the wholesale colocation page.
Entitlement and community
Read the zoning as written for the parcel, confirm whether a city or a county controls it, and check for a pending moratorium or ordinance. Data Center Watch's 2026 count of blocked and delayed projects shows permission is a live risk, not a formality.
Our site selection guide covers what to verify before a parcel goes under contract.
Connectivity
Which carriers physically serve the site, whether the building has diverse entry points, and what it costs to reach an interconnection hub if few carriers are nearby. Thin fiber can be fixed. The questions are who pays for the fix and how long it takes.
More in our data center connectivity guide.
Operations and certifications
Certifications checked with the issuing body, plus maintenance records, incidents, staffing and measured PUE. A facility's real track record is in its logs, not its marketing. When the deal includes an operating company and not only a building, security is its own review: breach history, access controls, backups and third-party exposure.
That work is covered under cybersecurity due diligence.
Buying an Operating Facility
An operating building carries a history the offering memorandum rarely prices. For facilities more than ten years old, four checks decide whether the price holds.
Remaining equipment life
UPS systems, batteries, chillers, switchgear and generators all have finite lives, and equipment installed 15 or more years ago is often near replacement. Build the replacement schedule from the maintenance records and put its cost in the early years of the model.
Ratings at the site, not on the nameplate
Nameplate ratings assume standard conditions. Generators lose output at altitude and in heat, and chillers lose capacity on the hottest days. Compare the derated figures with the IT load the seller is marketing.
The density ceiling
A building designed for 100 to 150 watts per square foot was built for enterprise racks. Serving AI tenants usually means new cooling, often liquid, and sometimes structural work. That cost, and the smaller pool of tenants the building can serve without it, belongs in the purchase price.
Built for one user
A facility built for a single corporate occupier may need separate security zones, metering, meet-me rooms and access control before it can serve several tenants. That conversion is real work, and it is often missing from the plan.
The price of an older facility should reflect its capital plan. A building that needs new UPS and chillers in years two and three should not be priced on its energized megawatts alone, and the review quantifies the gap for your model.
What we see in practice. Offering materials often present capacity as available when it is only a utility indication, not a contract. Lenders, appraisers and tenants underwrite the contracted figure, so we separate the two first. Vacant space is also often marketed as ready when it cannot support current AI densities without a retrofit nobody has priced.
Ten Red Flags We See Repeatedly
Each of these turns up in deal after deal, and each is cheaper to check before closing than after.
"Power available" with no signed utility agreement
The most common flag and the most expensive. Power that is not contracted, with dates, is a hope.
Utility capacity presented as IT capacity
About a third of the headline figure never reaches the racks. See the 7.5 MVA example above.
A cabinet count the power cannot serve
The hall is full on paper and empty in the market.
Floor loading given in PSI
Concrete strength is not load capacity. Ask for pounds per square foot from the structural drawings.
"Tier 3" without a certificate
A design intent is not a certification. Check the Uptime Institute registry.
A rent roll that does not match the leases
Escalators, free rent and expansion rights often read differently in the leases than in the summary.
Renewals at market with no reference
If "market" is not defined, the renewal rate in the model is a guess.
A transformer date nobody can produce
Without an order confirmation, the delivery date has nothing behind it.
Zoning confirmed by the seller, not the code
Read the ordinance itself and confirm which body controls the parcel.
Two carriers on the poles
Fine for a warehouse, thin for a data center. Price the fix before closing.
The Data Center Due Diligence Checklist: What to Request From the Seller
Diligence moves only as fast as the document requests. This is the list we send on day one, organized by the seven areas. Items tagged "Often missing" are the ones sellers most often cannot produce, and the gap is a finding in itself.
Power7 documents
- 1Executed utility service agreement with capacity, phasing dates and cost Often missing
- 2Will-serve or capacity letters
- 3Transformer and switchgear purchase orders with confirmed delivery dates Often missing
- 4The one-line diagram
- 5Generator and UPS specifications, ages and test records
- 6Fuel contracts
- 7The last twelve months of utility bills
Building and density5 documents
- 8Structural drawings with floor loading in pounds per square foot Often missing
- 9Mechanical drawings and the cooling plant specification, with chilled water temperature and flow at the rack
- 10The fire suppression design
- 11Roof and envelope condition reports
- 12The as-built set, not the permit set
Tenants and leases7 documents
- 13Every executed lease and amendment, not the abstract Often missing
- 14The rent roll with the power basis for each tenant
- 15Tenant estoppels
- 16Expansion and right-of-first-refusal schedules
- 17Outstanding delivery obligations
- 18SLA credit history
- 19Tenant financials or credit ratings
Market and demand3 documents
- 20The seller's market study and the assumptions behind the model's rates
- 21The pipeline of competing projects with contracted power
- 22Current quotes for comparable capacity in the market
Entitlement and community5 documents
- 23Zoning confirmation from the code, not a letter
- 24Permits issued and pending
- 25Any moratorium, pending ordinance or conditional-use condition Often missing
- 26Water and noise permits
- 27Tax abatement or incentive agreements and their clawbacks
Connectivity4 documents
- 28Carrier list with contracts
- 29Fiber entry drawings showing diverse paths
- 30Meet-me room design
- 31Dark fiber or metro circuit pricing to the nearest interconnection hub
Operations and certifications6 documents
- 32Certificates from the issuing bodies (Uptime, SOC 2, ISO, PCI) for this building Often missing
- 33Maintenance logs
- 34Incident and outage history
- 35Staffing and vendor contracts
- 36Measured PUE by month Often missing
- 37Insurance certificates and Phase I environmental site assessment
Who Hires Us for Due Diligence
Acquirers
Funds and operators buying an operating or partly built facility who need the offering memorandum tested independently.
Lenders and credit committees
Construction and acquisition lenders who need the power, timeline and rent assumptions verified and the risks ranked.
Investors and limited partners
A second opinion on a sponsor's plan, delivered before the capital call.
Developers and landowners
Owners of a site or a powered shell who want to know what it can serve and what to change before construction. See powered land, build to suit and our work with data center developers.
What you get
- A written report against the seven areas
- Every model assumption marked verified, unverified or contradicted
- The supporting documents for each finding
- Open items, ranked by the cost of being wrong
- A walkthrough call. If the deal is sound, the report says so.
How we work alongside your engineers and lawyers
We do not replace a structural or MEP engineer's inspection, or counsel's lease review. We frame the questions those professionals should answer, read their findings against the business plan, and cover the commercial and market questions neither is usually asked to address.
How Diligence Engagements Work
Fixed-fee consulting, paid by the client and scoped to the deal. We do no design or operations work, and we take no fee from operators or tenants on a diligence assignment. Findings are delivered in writing, with a call.
Acquisition diligence
An operating or partly built facility. A written report with the model's assumptions tested line by line.
Development and feasibility
A site or a planned building: power, tenant fit, market rates and what to change before construction. This is where our data center consulting practice began.
Lender and investor review
A second opinion on someone else's plan, scoped to the committee's questions.
A fixed fee, agreed in writing before work starts
Engagements start at $45,000. Multi-site and portfolio work is scoped separately and commonly runs into six figures.
The fee is set once we know what has to be verified and on what timeline. The written memo is delivered in three to six weeks, and no operator or tenant pays us on a diligence assignment.
Two practices, never on the same deal
When a company needs capacity rather than a building, we match it with an operator that fits, and that operator pays us. The two services are never combined on the same engagement.
Data Center Due Diligence FAQ
What is data center due diligence?
Data center due diligence is the independent verification an investor, lender or acquirer runs before committing capital. It checks whether the power is contracted or only promised, whether the building suits the tenants the plan assumes, whether the leases match the rent roll, whether the market supports the rates in the model, whether the use is permitted and will stay permitted, and whether operations match what the marketing claims.
What does a data center due diligence checklist include?
Seven areas: power (contracted capacity, dates and equipment orders); building and density (floor loading, cooling design and electrical topology); tenants and leases (escalators, power basis, renewals, expansion rights and credit); market and demand (vacancy, competing projects and achievable rates); entitlement and community (zoning, moratoriums and opposition); connectivity (carriers on site and diverse entries); and operations and certifications (certifications checked at the source, maintenance and incident records, and measured PUE).
What is the biggest risk in buying a data center?
Power described as available but not contracted. Utility interconnections for large campuses now take 24 to 48 months or more, and transformers can take more than three years, so power without dated paperwork cannot be underwritten. The second biggest risk is a building specification that cannot serve the tenants the business plan assumes.
How is data center diligence different from commercial real estate diligence?
A data center's value depends on power and density, not square footage. A 100,000 square foot building with 5 MW contracted is worth more than a 200,000 square foot building with 2 MW. Its tenant market depends on floor loading, cooling and electrical design rather than location and finish, and standard property diligence rarely tests any of these.
What should a lender verify before financing a data center?
Contracted power with dates and ordered equipment; capacity stated as IT load, not utility capacity; leases whose escalators, renewals and expansion rights match the rent roll; rates that tenants are actually signing in that market; and zoning, including any pending ordinance, that permits the use.
How much does data center due diligence cost?
Diligence is a fixed fee, paid by the client. Engagements start at $45,000. Multi-site and portfolio work is scoped separately and commonly runs into six figures. The fee is set in writing once we know the scope, and findings are delivered in writing.
How long does data center due diligence take?
It depends on what the seller provides and how quickly the utility and the municipality respond. A focused facility review can finish in weeks, and the written memo is typically delivered in three to six weeks. Verifying uncontracted power or a pending zoning matter can take longer, because the answer depends on outside parties. We say up front what can be verified within the deal's timeline and what cannot.
Can Metro Colo Advisory run diligence if it also places tenants?
Yes, and the two are kept apart. Diligence is a fixed-fee engagement paid by the client, with no operator or tenant fees on that assignment. Placement is a separate practice paid by the operator. We never do both on the same deal.
What documents should I request from a data center seller?
The executed utility agreement, with capacity and dates; transformer and switchgear orders with delivery confirmations; the one-line diagram; structural drawings with floor loading in pounds per square foot; the mechanical and cooling plant specifications; every lease and amendment, with the rent roll and estoppels; zoning confirmed from the code, plus any pending ordinance or moratorium; carrier lists and fiber entry drawings; certificates from the issuing bodies; maintenance and incident logs; and measured PUE by month.
How do you verify a data center's power capacity?
Read the utility agreement for contracted capacity, phasing and dates; confirm the equipment orders and their delivery dates; check the one-line diagram for what is installed and energized; and convert utility capacity to IT load. A 7.5 MVA service, for example, supports roughly 5 MW of IT load at a typical PUE. Power that is not papered goes into a later phase of the model.
What is the difference between technical and commercial data center due diligence?
Technical diligence tests the physical asset: power, cooling, structure, electrical topology and operations, usually through an engineer's inspection. Commercial diligence tests the business plan: leases, tenants, market rates, entitlements and timeline. Most deals fail on the commercial side, because the numbers in the model were never checked against signed agreements, and standard property diligence typically skips it.
Do I still need an engineering firm and a lawyer?
Yes, for the physical inspection and the legal lease review. We frame the questions those professionals should answer, test their findings against the business plan, and cover the commercial questions they are not asked: whether the capacity can be leased to the tenants the plan assumes, whether the assumed rates are being signed in that market, and whether the timeline holds given the utility and municipality involved.
What should I check when buying an older data center?
The remaining life of the UPS systems, batteries, chillers, switchgear and generators, and what replacing them costs in the first years of ownership; ratings at the actual site, since generators lose output at altitude and in heat and chillers lose capacity on the hottest days; the density ceiling, since a facility designed for 100 to 150 watts per square foot needs new cooling for AI tenants; and whether a building built for one occupier can be converted for several, which takes separate security zones, metering and meet-me rooms.
What is a data center feasibility study?
A feasibility study applies the same seven-area review to a site or a plan rather than an operating building. It assesses what the available power can support, which tenants the specification can serve, what the market will pay, how long the utility and permitting processes will take, and what to change before construction. It is where our data center consulting practice began.
The consulting practicedata center valuation, data center financing, data center consulting, cybersecurity due diligence, data center developers, powered land, powered shell, build to suit, site selection
The numbersdata center cost, colocation pricing guide, wholesale colocation, data center lease
The technical checkswhich providers are tier certified, data center tiers, direct to chip cooling, AI and GPU colocation, data center connectivity