Independent advisory for colocation, GPU and data center projects

A reply within one business day

Metro Colo Advisory research

AI Campus Power TrackerWhere America's AI data centers get their power, project by project

On-site gas plants, dedicated nuclear, restarts, fuel cells and batteries for 197 US data center power projects. 13.4 GW is under construction, and 79.7% of the planned power is built or contracted at the data center owner's cost rather than added to utility rates, as stated by the company or a filing. Plus the largest AI campuses ranked by power actually running. Every row links to its permit, filing or release.

0.6%
of the gas power planned for AI campuses is confirmed running: 431 MW of 71.1 GW of gas turbines and engines.
98.3GW
of dedicated power planned for named US data center campuses and sites
10.0GW
of nuclear contracted or agreed with data center buyers, including output from existing plants

"Running" means a dated source confirms it, so these are floors. Gas: 431 MW of 71.1 GW. All generation: 2.0 GW of 98.3 GW. Nuclear output from existing plants is not in the 98.3 GW. Full method below.

Explore the Map
Every row linked to its sourceFree CSV downloadFree under CC BY 4.0

Last updated Nov. 15, 2026.

AI data center power plants are the gas turbines, engines, fuel cells, batteries and nuclear deals that tech companies and developers are lining up so their campuses do not have to wait for the grid. We track 197 of them. The 142 that count toward our totals add up to 98.3 GW of dedicated power announced or planned. Under 1% of the gas power is running: 431 MW of 71.1 GW of gas turbines and engines (0.61%). Across all generation, 2.0 GW, or 2.0%, is confirmed running, plus 12 MW of batteries. 79.7% of the planned power is built or contracted at the data center owner's cost rather than added to utility rates, as stated by the companies and filings.

Metro Colo Advisory research

AI Data Center Power Plants: Every Project on One Map

Each bubble is one power plant or power deal tied to a data center campus, sized by megawatts and colored by fuel. Tap a bubble or a state, pick a filter, and the map, the totals and the table all follow. Every view has its own link you can share.

98.3 GWdedicated power announced or planned
2.0 GWgeneration confirmed running
2.0%of it confirmed running (batteries not counted)
10.0 GWnuclear contracted or agreed, including output from existing plants

On a phone, the state lookup below is easier than tapping the map.

Texas: the biggest pipeline, and a pause on new grid connections and permits

Global Energy Monitor counts 77 GW of planned gas plants in Texas meant to directly power data centers, out of 122 GW of gas in development statewide (GEM, Aug 2026). GEM counts plants statewide, including some not tied to a named campus, so it is larger than our Texas total and is not added to it.

On Aug 3 2026, Gov. Greg Abbott told the PUCT and ERCOT to audit data centers in the interconnection queue "before any additional data centers may move forward," pausing new data center grid connections until the audit is done (Akin Gump, Texas Public Radio). That letter covered grid connection only.

On Sep 21 2026 the governor widened the pause to permits: "Until they do, TCEQ will issue no permits sought by data center projects," he said, until the ERCOT and Texas Water Development Board audits are complete (Texas Public Radio). ERCOT expects to finish its audit in December. In our data, 8.8 GW of Texas projects are still listed as waiting on a permit.

Planned vs running

How Much of the Announced Power Is Running

Each bar is one technology, split by how far its projects have gotten. Switch to share to compare technologies of very different sizes.

Source: Metro Colo Advisory AI Campus Power Tracker, November 2026. Generation nameplate at full build, projects in the totals only.

Power-on calendar

When the Power Is Scheduled to Switch On

Projects grouped by the year each one says it will deliver its first power, sized by each project's full-build gigawatts. Running projects sit in the year they started. Tap a year to see the projects.

Each project's full-build megawatts sit in the year of its first phase, so a bar reads "projects totaling this much target first power that year", not "this much power arrives that year": most of it comes online in later phases. Projects whose date reads "not stated" or only "early 2030s" are filed as no date. Targets are the owners' own and often slip.

For the background behind these numbers, how data centers are powered covers grid, on-site and hybrid supply, data center power consumption shows what a campus draws, and data center power infrastructure follows the power from the utility feed to the rack.

Look up your state

Pick a state to see its projects, how many gigawatts are running and its next dated milestone.

Coming up

Dated hearings, decisions and deadlines after Nov 14, 2026, checked against primary sources where we could.

    Every project

    The Full AI Campus Power Plant List

    Sort by any column. The table follows the filters and search above.

    Source
    For reporters and researchers

    Download, Cite and Ask Us

    Download the data

    Every project with its megawatts, status, dates and up to three sources. CSV, free to use.

    Download CSV

    DOI: 10.5281/zenodo.24222718

    How to cite

    Metro Colo Advisory, "AI Campus Power Tracker," updated November 2026, https://metrocoloadvisory.com/data-center-power-plants/. DOI: 10.5281/zenodo.24222718. License: CC BY 4.0.

    Request data or comment

    We answer in writing, by email. A reply within 24 hours.

    Contact Us

    Free to use under a Creative Commons Attribution 4.0 license. Credit Metro Colo Advisory and link to this page.

    Method
    Need more than the download?

    The public file is free to use under CC BY 4.0. For a custom cut by market, operator or date, scheduled updates, or the fields we keep in-house and don't publish (exact coordinates and past snapshots), email us what you are working on. If it is a site, a deal or a lease, the same research backs our data center consulting.

    Request the Full Dataset

    How the Tracker Is Built

    • What counts. A power source built, contracted or planned for a specific, named data center campus: on-site gas turbines and engines, fuel cells, batteries, dedicated utility plants, power from an existing nuclear plant, nuclear restarts and new reactors. Solar, wind and storage count only when tied to a named campus. Generic corporate power purchase agreements do not.
    • Megawatts. Generation nameplate at full build, as stated in the primary source. Data center IT load is kept out of the megawatt column and noted separately. 33 projects have no stated megawatts; they appear on the map and in the table but add nothing to the totals. Where a figure is only a lower bound (the xAI Colossus 2 batteries, and the Meitner hybrid in Texas, which includes storage), the card says "at least". Where a regulator and a company give different figures, the regulator's figure is used and the other is noted.
    • Totals. "Dedicated power announced or planned" adds the 142 projects in our totals, whatever their status. "Generation confirmed running" adds the megawatts a dated source confirms are operating, on 10 projects (two count only the part confirmed: 10 of 80 engines at one, one of three solar sites at another), so it is a floor. One of them, Google's Quantum solar in Texas (640 MW), is counted on its owner's statement alone; without it, 1.36 GW is running. It leaves out about 1 GW of temporary xAI turbines at Southaven that are being retired. Batteries are reported separately (12 MW running) so storage never inflates generation, and rows whose MW is only an estimate (the Colossus 2 Megapacks, at least 720 MW from satellite imagery) are left out of every running figure. 55 rows are listed but not added: canceled projects, backup-only generators, turbines and batteries, programs with no named site, generation hubs and utility system plants with no named campus, Fermi America (announced tenant deal lapsed), a financial nuclear agreement that names no plant, stated ceilings beyond the permitted block, temporary units being replaced, likely double counts, and existing plants under contract. "Nuclear contracted or agreed" is output contracted or agreed from named existing nuclear plants plus restarts and uprates, all for named data center buyers; financial agreements that name no plant are not counted. Projects with no named tenant are counted when they are sited and permitted or announced by the owner, and say "not named". "Who pays" is as stated by the company or a filing: data center owner pays, shared, utility rate base or not disclosed. The existing-plant output is not in the announced total; the restarts and uprates are, so do not add the two figures. Deals not yet approved are counted at the low end of the stated range.
    • Tenants. Every row says how the data center buyer is known: named in a release, named in a regulatory filing, secondary reporting, owner-occupier, or not named. We never infer a tenant from an LLC name.
    • Sources. Permits, regulatory dockets and orders, SEC filings and company releases come first, then news reports. Each row lists up to three sources with what each one says. We use paid trackers only to learn that a project exists, never as a source.
    • Map. Locations are approximate to the town or site. Projects that disclose only a state are placed at the center of that state and marked approximate. Projects with no disclosed location are in the table.
    • Updates and corrections. We check every row monthly and record the date we last saw it in a source. To suggest a project or a correction, contact us.
    What this means for buyers

    What This Means If You Need Power Now

    In our view the headline for buyers is timing. Only 2.0% of the power in our totals is generation confirmed running, and 94% of the rest is dated 2027 or later or has no date at all. AI compute companies, GPU clouds and enterprise buyers below hyperscale rarely get first call on a new plant, so the practical question is which capacity is already powered, which sites have a credible path to power, and what that path costs.

    That is the work our data center consulting practice does: power strategy across grid, on-site and bridge power, for your engineer to confirm. If you need capacity sooner than these plants arrive, see AI and GPU colocation and wholesale colocation. If you are planning a campus with its own generation, see build to suit and powered land.

    Share My Power Requirement

    Data as of November 2026. Part of Metro Colo Advisory Research.

    Metro Colo Advisory research

    Largest Data Centers in the World, Ranked by Power Running

    The biggest AI compute campuses we can document, ranked by the megawatts a source says are running. The solid part of each bar is running; the lighter part is announced but not yet running. Where a source gives no running figure, we say "not disclosed" instead of guessing.

    Campuses tracked134in 21 countries
    Disclose running MW20 of 121AI campuses publish a running MW figure (134 tracked); the rest read "not disclosed"
    Running MW not disclosed101campuses in totals publish no running figure
    Largest capacity in service1,000 MWColossus I and II (Memphis and Southaven): GPU nameplate compute for the two sites together (SpaceX prospectus, as of Mar 31, 2026; not measured power draw)

    Why 121 of 134: the other 13 campuses overlap another entry, are paused or withdrawn, or state only a ceiling with no sited power, so they are listed but not added to the totals.

    Status chips describe build status: a campus can be running without publishing how many megawatts.

    RunningAnnounced, not yet runningRunning not disclosed
      Compare

      Compare Two AI Campuses

      Pick two campuses, or tap "Compare" on any campus card. Bars share one scale, and every comparison shows its math.

      vs
      For reporters and researchers

      Download and Cite the Campus List

      Download the data

      Every campus with running and announced megawatts, the basis for each figure, and sources with quotes.

      Download CSV

      DOI: 10.5281/zenodo.24222726

      How to cite

      Metro Colo Advisory, "Largest AI Campuses," updated November 2026, https://metrocoloadvisory.com/data-center-power-plants/#largest-ai-campuses. DOI: 10.5281/zenodo.24222726. License: CC BY 4.0.

      Request data or comment

      We answer in writing, by email. A reply within 24 hours.

      Contact Us

      Free to use under a Creative Commons Attribution 4.0 license. Credit Metro Colo Advisory and link to this page.

      Method

      How the Campus List Is Built

      • What counts. A named AI compute campus or supercomputer, anywhere in the world, with at least one public source for its power or its status.
      • Running megawatts. Power a source says is energized or in use at the campus. If no source gives a figure, the campus shows "not disclosed" and ranks after every campus with a figure. It is never counted as zero. Colossus I and II is shown at about 1,000 MW, the GPU nameplate compute SpaceX's prospectus gives for the two sites together as of March 31, 2026. It is installed GPU capacity, not power drawn. SpaceX's later company-wide figure (1.7 GW at Sept 30, 2026) names no site, so it is not used. Tesla Cortex 1 and 2 share one site and are shown together, as are Colossus I and II.
      • Announced megawatts. The full campus build the owner has stated. Where only a running figure exists, announced equals running. When an announced figure measures a power plant or a supply contract rather than the campus (5 campuses, such as GW Ranch and Homer City), the card shows it but it is not ranked or added; the plant is on the power plant tab with the same megawatts.
      • Disclosure gap. Only 20 of 121 campuses in our totals publish a running figure at all, so we do not headline a share of announced megawatts that is running. For reference: across the 19 campuses that publish both a running and an announced campus figure, running is 31.8% of announced. That is a small sample, mostly smaller public companies that report megawatts to investors, so it says little about the hyperscale campuses that disclose nothing. Figures are compared as published; on some rows running is IT load and announced is facility power.
      • Totals. 13 rows overlap another row, are withdrawn, stalled or paused, or state a ceiling with no tenant or sited power (Fermi America, PORTS-Pike), so they are listed but left out of the headline totals. Their cards say why. National lab supercomputers, multi-site programs and fleets are in the CSV download only.
      • Sources. Filings, regulator documents and company releases first, then news. Each card shows every source with one short quote; the full quotes are in the CSV download.
      • Corrections. To suggest a campus or a correction, contact us.

      Largest Data Center Questions

      What is the largest data center in the world?

      Ranked by the power a source says is running, the largest is Colossus I and II, SpaceXAI's AI campus in Memphis, Tennessee and Southaven, Mississippi. SpaceX says the two together provide about 1.0 GW of capacity (as of March 31, 2026). Its larger 1.7 GW figure counts installed GPUs across all of its data centers, not one site, and neither figure is measured power draw. Lists that rank data centers by building size in square feet name different sites, because floor area says little about how much computing a site actually runs.

      How is the size of a data center measured?

      By power, in megawatts. A campus can be measured as the IT load that reaches the servers, as total facility power including cooling, or as the grid capacity the utility has agreed to deliver, and the three are not the same number. This list ranks campuses by megawatts a source says are running today and shows announced megawatts separately, with the basis for each figure on every card.

      How many campuses does this ranking cover?

      131 AI campuses in 21 countries, each with its running and announced megawatts, the basis for each figure, and the sources with quotes. Campuses that overlap another row, are paused, or state a ceiling with no tenant or sited power are listed but left out of the headline totals.

      Campus list updated November 2026. Part of Metro Colo Advisory Research.

      Back to top and tabs