How Data Centers Are Powered
Grid, Gas, Solar, Nuclear, Fuel Cells and Batteries: What Runs Today and What AI Campuses Are Building

Most data centers run on the utility grid with diesel generators as backup. The new AI campuses are adding power of their own, and most of what they plan burns gas. Our tracker shows how little of it is running yet.

Plan Power for a Site
11 power sources compared Built on 197 tracked power projects Free to cite, CC BY 4.0

Updated November 2026. Every number links to its source.

ResearchUpdated November 2026Built on our AI Campus Power Tracker of 197 power projects

Most data centers are powered by the local utility grid, with UPS batteries and diesel generators standing by in case it fails. The new AI campuses are adding power of their own, led by gas. Our AI Campus Power Tracker counts 98.3 GW of dedicated power planned for named US data center campuses. 60% of it is gas turbines and gas plants, 72% once gas engines are added. Only 2.0 GW is confirmed running (1.36 GW without one 640 MW solar project counted on its owner's statement alone). Of the 71.1 GW of gas, 431 MW runs today: 0.61%.

This guide explains each way a data center gets power: the grid and why the wait for it is long, gas turbines and engines, Bloom Energy fuel cells, solar, wind and geothermal, nuclear restarts and small modular reactors, batteries, and backup generators. For each one it shows how fast it arrives, whether it runs around the clock, what it costs where a source gives a number, and real projects with their megawatts. If you are weighing these options for a specific site, our data center consulting team does that work.

Planned for AI campuses
98.3 GW
dedicated power for named US campuses, any status
Gas turbines and plants
60%
of the planned total; 72% with gas engines
Confirmed running
2.0 GW
2.0% of the planned total; 1.36 GW without one solar project counted on its owner's word
Planned gas running
0.61%
431 MW of 71.1 GW of turbines and engines

Source: Metro Colo Advisory, AI Campus Power Tracker, as of November 14, 2026. The planned total includes 1.5 GW of batteries; running counts generation only, because batteries store power rather than make it.

Weighing grid, gas or on-site power for a site?
Send us the site, the load and the date you need power. You'll hear back within 24 hours.
Send the Site Details

What Powers Data Centers Today

Data centers in operation today mostly buy their power from the utility and keep their own backup on site. What is changing is the largest new campuses. Some now build or contract a power plant of their own because the grid cannot deliver enough power by the date they need it. A campus can get power in four ways, and many combine them.

Grid service

Defaultutility tariff, firm or non-firm

The utility builds or upgrades a substation and delivers power under a tariff. Firm service is the norm; newer non-firm options connect sooner but can be cut in an emergency.

Behind the meter

31.4 GWplanned with a grid tie, in our tracker

A gas plant, fuel cells or engines on the data center's side of the meter, or a load wired directly to an existing power plant.

Contracted supply

PPApower purchase agreement

The data center owner signs for the output of a solar farm, wind farm or nuclear plant on the grid, for terms such as 20 years at Crane and Clinton, and the grid delivers it.

Backup on site

N+1

UPS batteries carry the load until diesel generators take over, and the generators run until the grid returns. POWER Magazine's guide to Uptime Institute's Tier III calls for N+1 redundancy on critical systems and at least 12 hours of generator fuel.

Sources: Metro Colo Advisory, AI Campus Power Tracker; POWER Magazine, Uptime Institute's Tier III Standard.

Data Center Power Sources Compared

No single source is fast, firm, cheap and clean at once, which is why large campuses mix them. Fuel cells arrive in months, gas engines in one to two years, large gas plants in three to seven, and nuclear restarts and new reactors later still. Solar and wind have the lowest levelized cost per megawatt-hour but run only part of the day, so they come paired with batteries, gas or the grid.

Power sourceHow it works for a data centerTime to powerRuns 24/7? (US fleet capacity factor, 2025)Cost signalReal examplesKey constraint
Grid (utility service)GridThe utility delivers power through a substation built or upgraded for the site; the data center pays a tariff.Four to seven years for 100 MW+ sites in Virginia (Dominion, 2024)Yes, on firm service. Non-firm service can be cut in emergencies$90 to $95 per MWh (Rabobank)Dominion: 12.2 GW of data center capacity under electric service agreements (September 2026)Interconnection queues and transmission upgrades
Gas turbinesOn site or utilityAeroderivative or heavy-duty turbines burn pipeline gas, on site or in a utility plant built for the campus.Aeroderivatives one to two years; heavy-duty and combined cycle 36 to 84 months (Rabobank)Yes, with firm gas supply. US combined-cycle fleet: 58.7%; combustion turbines 13.6%, mostly used as peakersCombined cycle $51 to $129; peaking $144 to $276 per MWh (Lazard)Homer City, PA: 4,678 MWe, under construction. Entergy for Meta Hyperion: more than 5,200 MW proposed. Socrates South for Meta, OH: 200 MW running, off grid. xAI Colossus 1: 198 MW runningTurbine backlog and slot reservations (GE Vernova 122 GW) and air permits
Gas enginesOn siteBanks of reciprocating engines, added in blocks as the load grows.12 to 24 months (Rabobank)Yes when run as baseload. US engine fleet: 18.0%Behind-the-meter power overall: $100 to $165 per MWh (Rabobank)Vantage TX1 (VoltaGrid): 33.1 MW running of 265 MW. South Valley, NV: 144 MW temporary engine plant for two to three yearsAir permits and the number of units to maintain
Fuel cellsOn siteModular solid oxide fuel cells turn natural gas into electricity next to the data hall.As little as 90 days (Rabobank); Oracle site in 55 days (Bloom)Built to run continuously. No EIA fleet figureAEP: about $4 billion for 702 MWOracle: up to 2.8 GW of Bloom. AEP for Google, Cheyenne: 702 MW. Project Jupiter (YGI Microgrid), NM: 2,462 MW proposedGas pipeline supply; AWS Hilliard's in-service date depends on it
Solar plus storagePPA or co-locatedA solar farm under contract on the grid, or built next to the campus with batteries to shift output.No common figure. Google's Quantum project began operations in June 2026, according to its developer, IntersectNo. US solar fleet: 24.0%Solar $40 to $98; solar plus storage $61 to $156 per MWh (Lazard)Google Haskell County, TX: 640 MW solar and 1.3 GWh storage. Faraday Solar for Meta, UT: 525 MW runningWeather, land, and the need for firm backup
WindPPA or co-locatedA wind farm under contract on the grid or paired with a campus.No common figureNo. US wind fleet: 33.8%Onshore wind $37 to $99 per MWh (Lazard)Goodnight 2 wind farm for Crusoe's Goodnight, TX campus: 265.5 MW under constructionVariable output
Nuclear: restarts and existing plantsPPA or co-locatedThe data center buys a plant's output under contracts of about 20 to 25 years, at a running plant or a restarted one.Crane: closed 2019, restart targeted 2027Yes. US nuclear fleet: 91.1%No contract prices publishedCrane for Microsoft: 835 MW. Susquehanna for Amazon: 1,920 MW. Clinton for Meta: 1,121 MW. Comanche Peak for Amazon: up to 1,200 MWFew plants available; NRC licensing; FERC co-location rules
Small modular and advanced reactorsPPA or utilityNew reactors contracted by data center owners, delivered through a utility or on a campus.First units 2030 (Kairos for Google) and early 2030s (X-energy for Amazon)Yes, once builtNo price published; Lazard puts new nuclear at $175 to $255 per MWhOklo for Meta, Pike County, OH: up to 1.2 GW. X-energy for Amazon: about 320 MW, option to 960 MWNo unit in our tracker is running yet
GeothermalPPA or utility tariffEnhanced geothermal wells feed a utility grid under a tariff or contract tied to the data center.Both XGS phases for Meta by 2030Yes. US geothermal fleet: 65.9%No sourced priceFervo for Google, NV: 115 MW. XGS for Meta, NM: 150 MWSuitable geology; projects so far are small
BatteriesOn site or utilityStore energy, not make it: ride through grid events, smooth AI load swings, shift solar output.No common figureNo. Hours of storage, then rechargeNo sourced priceDTE for Oracle's Saline Township, MI campus: 332 MW. Google Quantum: 1.3 GWhDuration; batteries are not counted as generation in our tracker
Diesel backup generatorsOn siteStart when utility power fails while UPS batteries carry the load; tested on a schedule.Installed with the buildingNo. Emergency use, limited by air permitsNo sourced priceMicrosoft La Porte, IN: 42 x 3,000 kWe plus 6 x 500 kWe in a draft permitEmission caps; at least 12 hours of fuel on site for Tier III, per POWER Magazine's guide

Sources: time to power from RaboResearch, The sprint and Data Center Knowledge (Bloomberg), Virginia power wait; capacity factors from EIA Electric Power Annual, Table 4.8.A and EIA Electric Power Annual, Table 4.8.B; cost from Lazard, Levelized Cost of Energy+ (July 2026) (unsubsidized levelized cost of new generation, not a delivered price) and RaboResearch, The sprint; examples from the project sources cited in each section below and the Metro Colo Advisory, AI Campus Power Tracker. Dominion figure from Dominion Energy Q3 2026 earnings call slides.

How much of the year each source produced in 2025
Nuclear91.1%
Geothermal65.9%
Gas, combined cycle58.7%
Wind33.8%
Solar photovoltaic24.0%
Gas, internal combustion engines18.0%
Gas, combustion turbines13.6%
Capacity factor is output as a share of what the fleet could make running flat out all year. Gold: weather or fuel-limited sources and nuclear; navy: gas. Low gas turbine and engine figures reflect how the US fleet is dispatched, mostly as peakers, not what an on-site unit built for baseload can do.

Sources: EIA Electric Power Annual, Table 4.8.A; EIA Electric Power Annual, Table 4.8.B.

What the New AI Campuses Are Building

Gas dominates what AI campuses plan, but almost none of it is running yet, while most of what does run is solar, wind and geothermal. Our AI Campus Power Tracker follows 197 power projects tied to named US data center campuses, each linked to its permit, filing or release. 142 of them count toward the totals below. Of 98.3 GW planned, 13.4 GW is under construction, 21.0 GW is permitted, 26.4 GW awaits a permit and 34.6 GW is announced only. 2.7 GW carries operating status, and 2.0 GW of generation is confirmed running. The last 0.2 GW is the running part of a plant still being built and one solar project whose construction status dates from 2020 and has not been re-confirmed.

Planned vs running: the power mix for named US AI campusesShare of megawatts by type. Planned counts every project in our totals at any status; running counts generation a dated source confirms is operating.

Planned: 98.3 GW

Gas turbines and gas plants 59.3 GW (60.4%)Gas engines 11.8 GW (12.0%)Solar, wind and geothermal 13.8 GW (14.1%)New reactors (SMR, advanced) 5.6 GW (5.7%)Fuel cells 3.3 GW (3.3%)Nuclear restarts and uprates 3.0 GW (3.0%)Batteries (storage) 1.5 GW (1.5%)

Confirmed running: 2,001 MW of generation

Gas turbines and gas plants 398 MW (19.9%)Gas engines 33.1 MW (1.7%)Solar, wind and geothermal 1,570 MW (78.5%)

Sources: Metro Colo Advisory, AI Campus Power Tracker.

How much of each planned type is runningLight bar: planned GW. Dark bar: MW confirmed running, on the same scale.
Gas turbines and gas plants
398 MW running of 59.3 GW (0.67%)
Gas engines
33.1 MW running of 11.8 GW (0.28%)
Solar, wind and geothermal
1,570 MW running of 13.8 GW (11.3%)
New reactors (SMR, advanced)
None confirmed running of 5.6 GW
Fuel cells
None confirmed running of 3.3 GW
Nuclear restarts and uprates
None confirmed running of 3.0 GW
Batteries (storage)
12 MW running of 1.5 GW (storage, not generation)

Source: Metro Colo Advisory, AI Campus Power Tracker, November 14, 2026. Existing nuclear plants under contract (7.0 GW) are kept out of the totals because those plants already run; restarts and uprates (3.0 GW) are in. Our tracker counts Google's Quantum solar project (640 MW) as running on its owner's statement alone; without it, 1.36 GW is running.

The timing is front-loaded: 22.0 GW is scheduled for first power in 2027 and 22.8 GW in 2028, with each project's full build filed under its first year. Owners also pay for most of it. For 79.7% of planned megawatts, the company or a filing says the data center owner pays for the power plant.

Data Center Interconnection: The Wait for Grid Power

Grid power is usually the cheaper and simpler supply for a data center, and in the busiest markets it is also the slowest to arrive. Requests to connect large loads far exceed what utilities have built or contracted. The gap between what is requested and what actually draws power is the subject of our AI Power Reality Check, which tracks 52 US utilities.

ERCOT large load queue

474 GW

of large loads seeking interconnection in Texas as of late July 2026, about 90% of them data centers. In September 2026, large loads approved to energize for 9,456 MW drew a combined monthly peak of 4,132 MW (each site's peak added together).

ERCOT Senate panel deck, July 29 2026; ERCOT Monthly Operational Overview, September 2026

Dominion Energy, Virginia

4 to 7 yearswait for sites needing more than 100 MW (2024)

Dominion now reports about 54.9 GW of data center capacity in stages of contracting as of September 2026, including 12.2 GW under electric service agreements.

Data Center Knowledge (Bloomberg), Virginia power wait; Dominion Energy Q3 2026 earnings call slides

Oncor, Texas

293 GWfrom data centers in its large load queue

795 requests in Oncor's transmission interconnection queue at the end of the third quarter of 2026.

Oncor Q3 2026 results (SEC exhibit 99.1)

Southern Company

21 GWof large load customers under contract

Against a prospective large load pipeline of over 75 GW.

Southern Company Q3 2026 earnings deck

This is why grid timing drives site value. A site with a signed service agreement and a substation date is worth more than one with a request in a queue, and the difference shows up in what powered shell buyers and build to suit tenants will pay.

Texas has added a pause on top of the queue. On August 3, 2026, Governor Abbott directed the PUC and ERCOT to run a "comprehensive verification and audit" of data centers in the interconnection process "before any additional data centers may move forward," which ERCOT said it could apply only to projects of at least 75 MW. On September 21 he extended the pause to environmental permits: "Until they do, TCEQ will issue no permits sought by data center projects." ERCOT expects to finish its audit in December.

Sources: Akin Gump, Texas pauses data center interconnections; Texas Public Radio, TCEQ permit pause for data centers.

Firm vs non-firm service

Grid operators are now offering faster connections in exchange for the right to cut a data center first. Firm service is the traditional promise of power at all times. Non-firm service connects sooner or costs less, and is curtailed ahead of other customers when the grid is stressed.

Non-firm options, in law or ordered

  • SPP CHILL: SPP says the service "does not provide a firm source of power," and loads on it are subject to curtailment, or loss of power in extreme circumstances.
  • PJM co-located loads: FERC ordered PJM to create Non-Firm Contract Demand service, which will be curtailed during emergency operations before firm customers.
  • Texas SB 6: for loads connected at transmission voltage after December 31, 2025, the utility must be able to curtail them during firm load shed. Critical industrial and critical natural gas loads are exempt.

Backup can be called on

  • Texas: in an energy emergency, after reasonable notice and after deploying all market services except frequency responsive services, ERCOT may have the utility require a large load (75 MW or more by default) with on-site backup able to serve at least 50 percent of its demand to run that backup or curtail. The law does not authorize breaking emissions limits.
  • Duke Energy, North Carolina (pending): a settlement would make new large loads interruptible, 95% of load for up to 50 hours a year or 50% for up to 100, during ramp-up plus one year, unpaid.
  • PJM and Duke, 2026: short federal emergency orders, a few days each, let PJM and Duke Energy direct backup generators, including those at data centers, to run as a last resort before cutting firm load.

Sources: SPP blog, innovation with large loads; Gibson Dunn on FERC's PJM co-location order; Texas SB 6 (89th Legislature), enrolled text; Duke Energy large load tariff settlement (NCUC); US DOE Order No. 202-26-50 (PJM); US DOE Order No. 202-26-07 (Duke Energy).

Behind the Meter Power, Explained

Behind the meter means the data center takes power from a generator on its own side of the utility meter instead of through the grid. It covers two different setups: a new plant built on or next to the campus, and a data center connected directly to an existing power plant, which regulators call co-located load. The appeal is speed. Rabobank counts more than 130 GW of behind-the-meter generation proposed across the US, over 80% of it gas, and puts its cost at $100 to $165 per MWh against $90 to $95 for grid power.

Sources: RaboResearch, The sprint.

1

November 2024: FERC rejects the Susquehanna expansion

PJM filed an amended interconnection agreement to raise the load co-located at the Susquehanna nuclear plant, which serves Amazon's data center, from 300 MW to 480 MW. FERC rejected the amended agreement, finding PJM had not shown the non-conforming terms were necessary.

2

June 2025: the deal moves in front of the meter

Talen agreed to supply Amazon 1,920 MW of nuclear power through 2042, moving to a front-of-the-meter arrangement after transmission reconfigurations that Talen expected in spring 2026.

3

December 18, 2025: new PJM co-location services

FERC found PJM's rules "unjust and unreasonable" for lacking clear co-location guidelines and directed two new transmission services, Firm Contract Demand and Non-Firm Contract Demand, plus an interim non-firm service ahead of full network service.

Sources: World Nuclear News, FERC rejects amended Susquehanna agreement; Talen Energy release, Amazon PPA; Jones Day on FERC's Dec 18 2025 co-location order; Gibson Dunn on FERC's PJM co-location order.

The definition that matters now is FERC's: co-located load is "end-use customer load that is physically connected to the facilities of an existing or planned [generator] on the [generator's] side of the Point of Interconnection." A campus that runs entirely on its own plant, with no grid tie, is a data center microgrid, or islanded. Our tracker counts 18.9 GW of planned power in that category, and 31.4 GW behind the meter with a grid tie.

How planned AI campus power connects to the gridShare of 98.3 GW planned for named US campuses, by grid relationship.
Behind the meter, with a grid tie 31.4 GW (31.9%)Utility plant dedicated to a campus 19.7 GW (20.0%)Off grid (islanded) 18.9 GW (19.2%)Grid PPA tied to a campus 11.2 GW (11.4%)Not stated 17.1 GW (17.4%)

Sources: Jones Day on FERC's Dec 18 2025 co-location order; Metro Colo Advisory, AI Campus Power Tracker.

Natural Gas: Turbines and Engines

Gas is the largest source of new power planned for data centers because it runs around the clock and can be built close to the load, but turbine supply is the bottleneck. GE Vernova's gas equipment backlog and slot reservations grew from 116 to 122 GW in the third quarter of 2026, and it expects at least 130 GW by year end. Akihiro Ondo, chief executive of Mitsubishi Power Asia Pacific, said of new gas turbine orders, "We're talking about delivery at around 2031."

Sources: GE Vernova Q3 2026 results; Energy Connects (Bloomberg), Mitsubishi Power on turbine deliveries.

Homer City, Pennsylvania

4,678 MWegas campus, under construction (air plan approved)

Seven GE 7HA.02 combined-cycle units plus up to ten Mitsubishi FT8 aeroderivatives at the former coal plant. DEP's review memo describes the project as "providing 4,678 MWe of dispatchable (on-demand) power." DEP notes the owner has publicly identified the potential for data centers on adjacent land; no specific use is confirmed.

PA DEP Plan Approval 32-00457A (Homer City); PA DEP technical review memo, Plan Approval 32-00457A (Nov 18 2025); PA DEP comment response document, Homer City (Nov 18 2025); Metro Colo Advisory, AI Campus Power Tracker

Meta Hyperion, Louisiana

5,200+ MWseven new utility gas plants proposed for one campus

Entergy Louisiana proposes seven new combined-cycle plants "totaling more than 5,200 megawatts" for the Hyperion expansion, with Meta-funded solar and batteries. That is on top of about 2.3 GW in three plants approved in 2025, for about 7.6 GW of utility-built gas in all (our tracker).

Entergy Louisiana release, Meta agreement; Metro Colo Advisory, AI Campus Power Tracker

xAI gas turbines, Memphis

15 turbinespermitted at Colossus 1, up to 247 MW

Shelby County granted xAI permits for 15 turbines in July 2025; our tracker counts 198 MW running, from the 12 turbines seen installed in September 2025. For Colossus 2, Mississippi approved 41 turbines at a permanent plant in Southaven in March 2026.

TechCrunch, xAI Memphis permits; Mississippi Free Press, Southaven turbines; Metro Colo Advisory, AI Campus Power Tracker

The largest running gas plant in our tracker is Socrates South for Meta's New Albany, Ohio campus: 200 MW of turbines and engines, not connected to the grid.

Gas engines are the modular alternative. Rabobank puts reciprocating engines and aeroderivative turbines at 12 to 24 months, against 36 to 84 months for heavy-duty and combined-cycle plants. At Vantage's TX1 campus, 33.1 MW of a 265 MW VoltaGrid engine plant was confirmed running in January 2026, 10 of 80 engines. Engines also serve as bridge power: in September 2026 Nevada approved a 144 MW temporary gas plant for the South Valley campus at 8990 USA Parkway in Sparks, expected to operate for two to three years. The proposal called for dozens of natural gas engines.

Sources: RaboResearch, The sprint; GovTech (Las Vegas Review-Journal), Nevada temporary gas plants; The Nevada Independent, South Valley temporary gas plant (Apr 29 2026); Metro Colo Advisory, AI Campus Power Tracker.

Gas tied to data centers extends well beyond named campuses. Global Energy Monitor finds that nearly two-thirds of the gas capacity in development in Texas, 77 GW, is planned to directly power data centers.

Sources: Global Energy Monitor, US gas proposals tied to data centers.

Data Center Fuel Cells and Bloom Energy

Fuel cells can be the fastest on-site power a data center can install, and Bloom Energy has signed the largest deals. Rabobank calls them "the only near-term option for immediate energization," deployable in as little as 90 days. Bloom says it delivered a fully operational system to Oracle in 55 days. Like gas plants, they run on pipeline gas: AWS's Hilliard, Ohio plant has an in-service date that depends on gas supply delivered by others.

Oracle

2.8 GW

Oracle intends to procure up to 2.8 GW of Bloom fuel cells; an initial 1.2 GW is contracted, with deployment underway.

Bloom Energy release, Oracle partnership

AEP for Google, Wyoming

702 MWnear Cheyenne, about $4 billion

Under a 20-year power purchase agreement, expected fully operational by the end of 2028.

AEP release, Cheyenne fuel cell project

Project Jupiter (YGI Microgrid), New Mexico

2,462 MWproposed fuel cell microgrid

Bloom solid oxide fuel cells "to power a nearby data center" south of Santa Teresa, in an air permit application that NMED lists as the YGI Microgrid. Oracle backs it as Project Jupiter's updated air permit.

NMED amended notice of hearing AQB 26-57; Oracle, comments on Project Jupiter's updated air permit application

Equinix and AWS

19 sitesEquinix data centers using Bloom (February 2025)

About 75 MW running and 30 MW under construction at Equinix as of February 2025, supplementing grid power. AWS Hilliard: 72.9 MW from 228 energy servers, due September 2027.

Bloom Energy release, Equinix; AEP Ohio Letter of Notification, OPSB 25-0649-EL-BLN

Brookfield has committed up to $5 billion to deploy Bloom fuel cells for AI data centers. In our tracker totals, fuel cells make up 3.3 GW of planned power and none is yet confirmed running at a named campus. Equinix's 75 MW across 19 sites and Oracle's program are portfolio rows we list but do not add, because they name no single campus.

Sources: Bloom Energy release, Brookfield; Metro Colo Advisory, AI Campus Power Tracker.

Solar, Wind, Geothermal and Batteries

Renewables are most of the dedicated data center power actually running today, but because solar and wind run only part of the day, a solar powered data center still needs batteries, gas or the grid. In our tracker, 78.5% of the generation confirmed running at named campuses is solar, wind or geothermal, or about 68% without Google's Quantum solar, which is counted on its owner's statement. Most of it reaches the data center through a power purchase agreement with a farm on the same grid rather than a direct wire.

Google, Haskell County, Texas

640 MWsolar plus 1.3 GWh storage, co-located

Intersect says its Quantum project began operations in June 2026, beside a Google data center under construction. It is the largest running solar our tracker counts, on the owner's statement alone.

Intersect, Google Texas data center and energy; Intersect, Quantum project page

Meta, Eagle Mountain, Utah

525 MWFaraday Solar, running

The largest running solar plant tied to a data center that a dated independent source confirms, supplied through the utility under a long-term agreement.

Metro Colo Advisory, AI Campus Power Tracker

Crusoe, Goodnight, Texas

265.5 MWGoodnight 2 wind, under construction

Paired with the Goodnight campus next to an operating first wind farm.

Metro Colo Advisory, AI Campus Power Tracker

Geothermal for Google and Meta

115 + 150 MWNevada (Fervo) and New Mexico (XGS)

Google's 115 MW of "around-the-clock" enhanced geothermal for NV Energy's grid, and XGS's 150 MW for Meta on the PNM grid, both phases by 2030.

Google, Nevada clean energy; ESG Today, Meta and XGS geothermal

Batteries for Oracle, Michigan

332 MWthree DTE battery projects

Fish Creek (132 MW), Cold Creek (100 MW) and Pine River (100 MW) will support the Saline Township campus, with Oracle covering the cost over 15 years.

Energy-Storage.news, DTE and the Oracle data center; Metro Colo Advisory, AI Campus Power Tracker

Cochise County, Arizona (proposed)

Up to 6,000 MWof load (electricity use) at full buildout

A SpaceX-linked application by Tombstone Resources LLC for a data center and battery storage campus on about 750 acres with dry cooling. No decision yet; not in our tracker totals.

KJZZ, SpaceX behind proposed Cochise County data center; KOLD, proposed data center in Cochise County

Batteries store power rather than make it, so our tracker keeps them out of generation totals. On a campus they ride through grid disturbances, smooth the fast load swings of AI workloads, and shift solar output into the evening.

Sources: Vertiv, Advanced UPS controls for AI workloads (Dec 2025); Intersect, Google Texas data center and energy.

Nuclear Power for Data Centers

Nuclear is the one source that is both carbon-free and runs nearly all year, and data center owners are buying it three ways: contracts with running plants, restarts of closed ones, and new small modular reactors. The US nuclear fleet ran at a 91.1% capacity factor in 2025. Our tracker counts 10.0 GW of nuclear contracted or agreed with named data center buyers: 7.0 GW from existing plants plus 3.0 GW of restarts and uprates. New reactors are on top of that and further out.

Sources: EIA Electric Power Annual, Table 4.8.B; Metro Colo Advisory, AI Campus Power Tracker.

Crane Clean Energy Center (Three Mile Island Unit 1)

Crane is the former Three Mile Island Unit 1 in Pennsylvania, which closed for economic reasons in 2019. Constellation is restarting it under a 20-year power purchase agreement with Microsoft. The restart is pending Nuclear Regulatory Commission licensing approvals, and PJM gave its interconnection request accelerated approval.

Capacity
835 MW
of carbon-free power returned to the grid
Buyer
Microsoft
20-year power purchase agreement, signed September 2024
Restart
2027
moved up from the original 2028 target
Federal loan
$1 billion
DOE loan closed in November 2025

Sources: Constellation, Crane Clean Energy Center announcement; Constellation, Crane one year later; US DOE, loan to restart Crane.

Talen and Amazon at Susquehanna

Talen will provide Amazon 1,920 MW of nuclear power through 2042 from the Susquehanna plant, after FERC turned down the expanded behind-the-meter version of the deal. The companies also plan to explore small modular reactors and uprates.

Sources: Talen Energy release, Amazon PPA.

Meta nuclear deals

Meta says its nuclear agreements support up to 6.6 GW of new and existing clean energy by 2035, the result of a nuclear request for proposals. They include 1,121 MW from Constellation's Clinton plant in Illinois for 20 years from June 2027, more than 2.1 GW from Vistra's Perry and Davis-Besse plants plus 433 MW of uprates, up to 1.2 GW from an Oklo campus in Pike County, Ohio that may come online as early as 2030, and two TerraPower Natrium units of up to 690 MW as early as 2032, with rights to six more.

Sources: Meta newsroom, nuclear energy projects; Constellation, Meta Clinton agreement.

Other restarts and contracts

Duane Arnold, Iowa

615 MWrestart for Google by Q1 2029

A 25-year power purchase agreement with Google and a federal loan of up to $1.9 billion.

Fox Business, Duane Arnold restart loan

Comanche Peak, Texas

Up to 1,200 MWfor Amazon, 20 years

Delivery to begin in the fourth quarter of 2027 and ramp to full capacity by 2032.

World Nuclear News, Vistra PPAs

SMR data center deals

None of the small modular reactors contracted for data centers is running yet. The first are scheduled for 2030.

Google and Kairos Power

50 MWHermes 2 on TVA's grid, operations 2030

Part of Google's aim to unlock up to 500 MW of nuclear power with Kairos.

Google, Kairos Power and TVA

Amazon and X-energy

About 320 MWfirst phase with Energy Northwest, early 2030s

With the option to increase to 960 MW. In Indiana, Amazon and AEP agreed to explore 12 Xe-100 reactors, 960 MW, at the former Breed coal plant site.

Amazon, X-energy and Energy Northwest SMRs; Amazon, X-energy and AEP in Indiana

Meta, Oklo and TerraPower

Up to 1.2 GWOklo campus, Pike County, Ohio

Oklo as early as 2030; TerraPower Natrium units as early as 2032.

Meta newsroom, nuclear energy projects
Is power the open question on your site?
Send us the site, the load and the date you need power. We'll tell you which paths are realistic and what each one changes in value. You'll hear back within 24 hours.
Send the Site Details

Data Center Generators and Backup Power

Data centers keep diesel generators on site to carry the facility if the grid fails, with UPS batteries bridging the gap until they start. POWER Magazine's guide to Uptime Institute's Tier III says the design must have standby generators and at least one backup component for every critical system (N+1), so any one can be serviced without losing protection. The same guide says the generators "should have enough fuel storage for at least 12 hours of operation."

Sources: POWER Magazine, Uptime Institute's Tier III Standard.

Microsoft, La Porte, Indiana

48 generators

A draft air permit lists 42 diesel emergency generators of 3,000 kWe and six of 500 kWe, about 129 MW of rated output (our math). Total NOx from all 48 "shall not exceed 95 tons per twelve (12) consecutive month period."

IDEM draft air permit F091-50526-00197, Microsoft La Porte

Nameplate is not permission to run

Emission capslimit how much backup can run

The permit sizes the fleet for an outage but caps its emissions over a year, so the generators can protect the site without serving as a power plant. On-site gas plants at AI campuses are permitted as primary power, under their own limits.

IDEM draft air permit F091-50526-00197, Microsoft La Porte

When the grid calls on backup

Oct 13 to 16, 2026DOE Order 202-26-50 for PJM

PJM was authorized to direct backup generation to operate "as a last resort before declaring an EEA 3." The order notes it may result in exceedance of permit restrictions.

US DOE Order No. 202-26-50 (PJM)

Installed totals also overstate the load a site can carry or lease. With N+1, for example four modules of which three are needed, the installed total is a third more than the usable load; with 2N it is double.

What happens when data centers switch to backup

On July 10, 2024, a failed lightning arrestor on a 230 kV line caused six faults in 82 seconds. About 1,500 MW of data center load transferred to backup power at once, and about 1,260 MW did not return to the grid for hours, according to NERC's review. Grid frequency and voltage rose with the load loss. NERC warns of issues in future incidents "if the load is not reconnected in a controlled manner."

The return is its own event. Vertiv notes that generators and some grid operators "can only tolerate a limited rate of power variation," and that exceeding it can make a generator read the swing as a fault. In May 2026 NERC issued a Level 3 alert on computational loads covering modeling, studies, instrumentation, commissioning, operations, protection and control, with responses due August 3, 2026.

Sources: NERC Incident Review, Large Load Loss; Vertiv, Advanced UPS controls for AI workloads (Dec 2025); Renewable Energy World, NERC Level 3 alert.

Green and Sustainable Data Centers

A green data center usually means its electricity use is matched by contracts for renewable or carbon-free power, and the key question is whether that match is counted over a year or hour by hour. Annual matching buys as many clean megawatt-hours as the data center uses over the year. Hourly matching, often called 24/7 carbon-free energy and reported by Google as carbon-free energy on an hourly basis, compares clean supply with use hour by hour, which is harder to reach.

Google

65%carbon-free energy on an hourly basis, 2025

Down from 66% in 2024, as Google's total electricity consumption grew 37% in 2025.

Google 2026 Environmental Report

Amazon

100%of electricity matched with renewables, 2025

For the third consecutive year, matched over the year.

Amazon Sustainability, carbon-free energy

Meta

100%of owned and operated data center and office electricity matched

With clean and renewable energy, as Meta states it; the page gives no year.

Meta Sustainability, data centers

Data center PPAs

The power purchase agreement is the main tool. Microsoft's framework with Brookfield covers more than 10.5 GW of new renewable capacity between 2026 and 2030, which the companies said in May 2024 was nearly 8 times larger than the largest single corporate PPA signed up to then. Nuclear contracts such as Crane, Clinton and Comanche Peak are PPAs too, and they are how buyers add firm carbon-free power that runs at night.

Sources: ESG Today, Microsoft and Brookfield.

Weighing grid, gas or on-site power for a site?
Send us the site, the load and the date you need power. Our data center consulting work covers power path, timing and value for powered shell and build to suit projects. You'll hear back within 24 hours.
Send the Site Details

Frequently Asked Questions

How are data centers powered?

Most data centers run on power from the local utility grid, with UPS batteries and diesel generators as backup if the grid fails. The newest AI campuses are also adding power of their own. Our AI Campus Power Tracker counts 98.3 GW of dedicated power planned for named US campuses, about 60% of it gas turbines and gas plants, but only 2.0 GW of it is confirmed running (1.36 GW without one 640 MW solar project counted on its owner's statement).

What powers data centers besides the grid?

Gas turbines and gas engines, fuel cells, solar and wind farms under contract, batteries, geothermal and nuclear. Gas leads what AI campuses are planning. Fuel cells can be the fastest to install, with Bloom Energy saying it delivered a working system to Oracle in 55 days. Nuclear arrives through contracts with existing plants, restarts such as Crane, and small modular reactors scheduled for 2030 and later.

Do data centers have backup generators?

Yes. Most use diesel generators, with UPS batteries carrying the load until the generators take over. POWER Magazine's guide to Uptime Institute's Tier III says the design needs standby generators, N+1 redundancy on critical systems and fuel for at least 12 hours. Air permits limit how much they can run: Microsoft's draft permit for La Porte, Indiana covers 42 generators of 3,000 kWe and six of 500 kWe under one 95-ton-a-year cap on nitrogen oxides.

Can a data center run on solar power?

Not around the clock on solar alone. US solar farms produced 24.0% of their capacity over 2025, according to EIA, so solar campuses pair it with batteries and the grid. The largest co-located example we track is Google's Haskell County, Texas campus, with a 640 MW solar and 1.3 GWh storage facility next to the data center, which its developer says began operating in June 2026. Most data center solar is bought through power purchase agreements from farms elsewhere on the grid.

What is behind the meter power for a data center?

Power the data center gets from a generator on its own side of the utility meter instead of through the grid: an on-site gas plant, fuel cells, or a load connected directly to an existing power plant. FERC rejected an expanded behind-the-meter deal at the Susquehanna nuclear plant in November 2024, and in December 2025 ordered PJM to create firm and non-firm transmission services for such co-located loads.

Are data centers using nuclear power?

Yes, mostly through contracts. Microsoft signed a 20-year agreement for the 835 MW Crane Clean Energy Center, the former Three Mile Island Unit 1, with the restart moved up to 2027. Talen will supply Amazon 1,920 MW from Susquehanna through 2042, and Meta says its deals support up to 6.6 GW by 2035. New small modular reactors for data centers are scheduled from 2030 onward.

How long does it take to get grid power for a large data center?

Years in the busiest markets. In 2024, Dominion Energy's wait for Virginia sites needing more than 100 MW reached roughly four to seven years. In Texas, ERCOT tracked about 474 GW of large loads seeking interconnection in July 2026, about 90% of them data centers, while loads approved to energize for 9,456 MW drew a combined monthly peak of 4,132 MW in September 2026. Texas also paused new data center grid connections on August 3, 2026, pending a statewide audit.

Can a data center run completely off the grid?

Yes, if it builds enough power of its own, usually gas. Our tracker counts 18.9 GW of planned power for campuses that will run off grid, or islanded, with no grid tie. One is running: Socrates South, a 200 MW gas plant for Meta's New Albany, Ohio campus that is not connected to the grid. An islanded campus has no utility to fall back on, so its own plant has to carry the backup role as well.

Who pays for a data center's power plant?

Usually the data center owner. For 79.7% of the planned megawatts in our tracker, the company or a filing says the data center owner pays for the power, as stated and not audited. In Michigan, for example, Oracle is covering the cost of three DTE battery projects for its Saline Township campus over 15 years.

Cite this page

Metro Colo Advisory, How Data Centers Are Powered, updated November 2026, https://metrocoloadvisory.com/how-data-centers-are-powered/

Free to use in news coverage and research with credit to Metro Colo Advisory and a link to this page, under a Creative Commons Attribution 4.0 license.

Our power data: AI Campus Power Tracker, every dedicated power project for named US campuses with its permit or filing.

Grid reality: AI Power Reality Check, data center power requested, signed and running at 52 US utilities.

How much power: data center power consumption, what a megawatt figure means and how much data centers use.

Method and corrections

Tracker figures come from Metro Colo Advisory's AI Campus Power Tracker as of November 14, 2026: rows in totals at any status, with running capacity counted only when a dated source confirms operation; batteries and floor estimates are excluded from running generation. Other figures were read from the linked sources in November 2026. Capacity factors are EIA's 2025 utility-scale averages. Cost ranges are Lazard's unsubsidized levelized costs of new generation (LCOE+, July 2026), not delivered prices. ERCOT large load figures are from ERCOT's September 2026 operational overview. To report a correction, contact us.