Independent advisory for colocation, GPU and data center projects

A reply within 24 hours

Texas Data Centers
Dallas-Fort Worth, Houston, Austin and San Antonio, the AI Campuses in West Texas, and What the 2026 Pause and the Election Mean for Your Timeline

Texas is building more data center capacity than any other state. In 2026 it paused new large-load approvals and state permits for data center projects, and the governor-elect has called for a moratorium until lawmakers act. We find Texas space that has power on your date, in an existing building or a new one, at no cost to you.

Price My Texas Requirement
For colocation, wholesale and AI requirements Power dates confirmed, not assumed Paid by the provider, never by you

Texas data centers span four established colocation markets, Dallas-Fort Worth, Houston, Austin and San Antonio, plus a wave of AI campuses in West Texas and the Panhandle, including the Stargate site in Abilene. Texas leads the country in capacity under construction, about 26 GW by JLL’s mid-2026 count. The constraint is now power and politics. ERCOT’s large-load queue reached roughly 474 GW, and in 2026 the state paused new data center interconnection approvals (August 3) and then state permits for data center projects (September 21) while it audits power and water use. On November 3, voters elected Gina Hinojosa governor, who has called for a moratorium on new data center construction until the Legislature passes new protections. Space in existing, energized buildings is unaffected; new projects face a slower and less certain path.

Searches for data centers in Texas usually mean one of two things: colocation space for a company that needs cabinets, cages or a few megawatts, or the AI build-out that has made the state the center of new construction. This page covers both: the Texas markets and what each is good for, the AI data centers in Texas and their status, the 2026 pause and the election, how ERCOT and the 2025 law known as SB 6 shape power, and how to get space. Market detail is on Dallas colocation, Houston colocation and Austin and San Antonio data centers.

UNDER CONSTRUCTION
~26 GW
in Texas, about double Virginia's 13 GW (JLL, mid-2026)
ERCOT QUEUE
~474 GW
of large-load requests, mostly data centers (August 2026)
RECORD PEAK
91,134 MW
ERCOT's all-time demand record, July 22, 2026 (preliminary)
AT RISK
~13.3 GW
of announced Texas projects a moratorium could put at risk (Jefferies)

Sources: JLL via the Houston Business Journal (August 2026); Utility Dive on the queue audit; ERCOT July 2026 operational overview; Jefferies via Fast Company. Page updated November 4, 2026.

Need space in Texas? Why talk to us before you call an operator
Power dates checked.
With new approvals and permits paused, an energized hall is worth more than a promised one. We confirm what is powered and when.
The right market.
DFW for interconnection and wholesale, Houston for energy and Gulf Coast companies, Austin and San Antonio for tech and lower cost, West Texas for scale.
Wholesale and AI fluent.
From a few cabinets to multi-megawatt and liquid-cooled requirements, matched to buildings that can deliver them.
No cost to you.
The operator you choose pays us. Your rate is not marked up, and you'll hear back within 24 hours.

The 2026 Pause and the Election: What Happens Next

Texas spent the second half of 2026 tightening the path for new data centers, and the November election added a new governor who wants to go further. Here is the sequence, and the dates that decide what comes next.

DateWhat happenedWhat it means
Aug 3, 2026Governor Abbott ordered ERCOT to audit data centers in its large-load queue, covering power and water use, tax breaks, ownership and community impactERCOT delayed its Batch Zero study, effectively pausing new interconnection approvals
Sep 14, 2026Abbott directed the Texas Water Development Board to penalize data centers that skip its water-use surveyWater reporting became a condition for state permits
Sep 21, 2026Abbott ordered the TCEQ to stop issuing permits for data center projects until the ERCOT and water audits are done, and told other agencies not to advance approvalsThe pause now reaches projects with their own on-site power, not just grid connections
Nov 3, 2026Gina Hinojosa was elected governor. She has called for a moratorium on new data center construction until the Legislature passes protectionsHer proposals include ending the sales tax exemption, letting local officials reject projects, and keeping data centers from raising household bills
Dec 10, 2026ERCOT is scheduled to present its audit findings to the Public Utility CommissionThe first point at which the permit pause could start to lift
Dec 2026The PUC expects a final decision on how much of transmission costs large loads must pay (Project 58000)Sets part of what new large projects pay for grid upgrades
Jan 2027The Legislature convenes January 12 and the new governor takes officeChanges to tax exemptions, local zoning powers or a statewide moratorium would run through this session

Sources: Texas Tribune on the August, September 14 and September 21 orders; Bracewell on the permit pause; Texas Public Radio on the December 10 presentation; Yahoo Finance on the AP's call of the race; the Hinojosa campaign on her proposals; Fast Company on a governor's powers; Ballotpedia on the session start. The PUC rulemaking is tracked in our data center electric rates tracker, with every Texas filing.

What a governor can do alone

Set priorities and direct state agencies within existing law, as the September 21 order did. Ending tax exemptions or expanding county zoning powers needs the Legislature.

What is not affected

Existing data centers keep operating, and space in energized buildings can still be leased. Projects that already hold their permits appear to fall outside the September order.

What is most exposed

New and early-stage projects that still need permits or a grid connection, including campuses planning their own on-site power.

WHAT IT MEANS FOR YOU
If you need Texas capacity in the next 12 to 18 months, focus on buildings that are already energized or already permitted, and get the power date in writing. If you own or are buying a Texas site, sites with permits and a power agreement in hand are worth more today than sites still waiting on either. We look at both sides: see powered land and data center due diligence.

Texas Data Center Markets

MarketWhat is thereBest for
Dallas-Fort WorthThe state's largest market: carrier hotels downtown, wholesale campuses in Richardson, Garland, Plano, Allen and Red OakInterconnection, enterprise and wholesale colocation
HoustonThe 1301 Fannin carrier hotel and suburban campuses, close to the energy industryEnergy, healthcare and Gulf Coast enterprises
AustinSwitch, CyrusOne, Digital Realty and DataBank, with growth in Round Rock and San MarcosTech companies and Central Texas enterprises
San AntonioMicrosoft's major hub and CyrusOne's Westover Hills campus, with new wholesale campusesLower-cost capacity and recovery for other Texas sites
West Texas and the PanhandleStargate in Abilene, Vantage's Frontier campus, and planned campuses near Amarillo and in the Permian BasinHyperscale AI campuses, mostly built for a single tenant
Distance from Dallas to the other Texas markets
Minimum round-trip latency over fiber, milliseconds
Abilene277 km
~2.8
Austin293 km
~2.9
Houston362 km
~3.6
San Antonio406 km
~4.1
Amarillo538 km
~5.4

MCA calculation from straight-line distance, about 1 ms round trip per 100 km; real fiber routes are longer. Free to cite with a link to this page.

Need space in Texas?
Send power, cabinet or megawatt count, connectivity needs and date. You'll hear back within 24 hours with the Texas buildings that fit.
Price My Texas Requirement

AI Data Centers in Texas

Texas attracts AI campuses for the same reasons it attracts every large industrial load: land, a fast-growing grid, natural gas, and a regulatory culture built for big projects. Most of these campuses are single-tenant builds for hyperscalers and AI labs rather than colocation, but they set the pace for the whole state.

MAJOR AI CAMPUSES IN TEXAS
Stargate, AbileneVantage Frontier, near AbileneFermi America, AmarilloGW Ranch, Pecos County
CampusWho and wherePlanned scaleStatus, October 2026
Stargate AbileneOpenAI and Oracle, developed by Crusoe on the Lancium site in AbileneAbout 1.2 GWBuildings online since 2025, ramping through 2026
FrontierVantage Data Centers, near AbileneAbout 1.4 GWUnder construction
Project MatadorFermi America, near AmarilloUp to about 11 GW plannedDelayed; construction paused in early 2026
GW RanchPacifico Energy, Pecos CountyAbout 7.65 GW, planned with its own generationPlanned

Sources: ERCOT queue tracker, Compute Law, ROC Telecom. Project scales are as announced and may change.

For a company placing GPUs rather than building a campus, the practical options are liquid-cooled halls in DFW and San Antonio, and smaller AI-ready colocation across the state. See AI and GPU colocation and GB200 and GB300 NVL72 for what high-density racks require.

Power: ERCOT, SB 6 and the 2026 Pauses

Most of Texas runs on ERCOT, a grid largely separate from the rest of the country. Its large-load queue grew from about 63 GW at the end of 2024 to roughly 474 GW by August 2026, more than five times the grid's record peak. Only a small fraction is real: by spring 2026 about 9 GW had approval to energize.

SB 6 (2025)

Sets the rules for loads of 75 MW and more: interconnection standards, financial security, disclosure of duplicate requests, and mandatory curtailment readiness for large loads connecting from 2026.

Batch Zero

A new process approved in June 2026 to study the first group of large-load projects together, with security deposits of about $50,000 per MW.

The 2026 pauses

The August 3 audit order effectively paused new interconnection approvals, and the September 21 order paused state permits for data center projects until the audits are done.

Sources: Utility Dive, Global Data Center Hub, Texas Tribune, ERCOT. Rules are still being finalized by the Public Utility Commission.

FOR COLOCATION
Colocation in existing, energized buildings is not affected by the pauses. New multi-megawatt and AI requirements should confirm the hall's energization date in writing, and consider buildings already through interconnection.

Texas Data Center Incentives

Texas exempts qualifying data centers of at least 100,000 square feet that meet investment and job thresholds from state sales and use tax on qualifying equipment, with local tax also exempt for qualifying large projects of at least 250,000 square feet. Texas has no state income tax. Those incentives are now in question from both parties: Governor Abbott has said he will work with the Legislature to end data center incentives, and Governor-elect Hinojosa has called for ending the sales tax exemption. For tenants, any change shows up through the operator's costs rather than as a direct charge.

Sources: Bracewell; the Hinojosa campaign.

What Texas Colocation Costs

Texas markets generally price below Northern Virginia and Chicago, with Dallas and San Antonio among the more affordable large markets for wholesale space. Retail cabinets in the Dallas and Houston carrier hotels cost more than suburban campuses. Current figures are on the colocation pricing guide and each market page.

Who Texas Data Centers Suit

National enterprises

Central location with good latency to both coasts; DFW is a common primary or recovery site.

Energy and industrial companies

Houston's ecosystem and proximity to operations.

AI and GPU deployments

Scale and liquid-cooled capacity, with power dates checked.

Companies leaving cloud or their own server rooms

Lower costs than coastal markets. See cloud repatriation.

Texas and Other Markets

Texas pairs with Atlanta, Phoenix and Virginia for national footprints, and with Mexico for companies serving both sides of the border. For a recovery site, Dallas and Houston back each other up, and Austin and San Antonio sit between them.

How We Find Space in Texas

1

You send the requirement

Power, cabinet or megawatt count, connectivity, cooling and date. You'll hear back within 24 hours.

2

We find what is powered

Which Texas halls have space and energized power for your date, including space that is not advertised.

3

We negotiate and you sign

Rate, power dates, term and exit terms negotiated before you sign. The operator you choose pays us.

NEED IT IN WRITING?
Evaluating a Texas site, a large deployment or a build-versus-lease decision for investors or a board? We run fixed-fee market, power and site analyses. See data center consulting.

Frequently Asked Questions

How many data centers are in Texas?

About 600 by one directory count, concentrated in Dallas-Fort Worth, Houston, Austin and San Antonio, with large new AI campuses in West Texas and the Panhandle. Texas also leads the US in capacity under construction, about 26 GW by JLL's mid-2026 count.

Where are most data centers in Texas?

Dallas-Fort Worth is the largest market, followed by Houston, Austin and San Antonio. The newest large campuses are in West Texas, around Abilene, and planned near Amarillo and in the Permian Basin.

Did Texas pause data center approvals?

Yes, in two steps. On August 3, 2026, Governor Abbott ordered an audit of data centers in ERCOT's large-load queue, which had reached about 474 GW, and ERCOT delayed its Batch Zero study, effectively pausing new interconnection approvals. On September 21, he ordered the TCEQ to stop issuing permits for data center projects until the power and water audits are done. Existing data centers keep operating.

Is there a data center moratorium in Texas?

Not a statewide ban in law. The September 21 order pauses state permits for data center projects until the audits are finished, and Governor-elect Gina Hinojosa has called for a moratorium on new data center construction until the Legislature passes new protections. Ending tax exemptions or changing local zoning powers would need the Legislature, which convenes January 12, 2027.

What does Gina Hinojosa's election mean for Texas data centers?

She takes office in January and has called for a moratorium on new data center construction until lawmakers pass protections, an end to the sales tax exemption, a say for local officials, disclosure of water and power use, and protection for household bills. A governor can direct state agencies within existing law; most of the rest needs the Legislature. Existing, energized data centers keep operating.

When will the Texas data center pause end?

No end date has been set. The permit pause runs until the ERCOT and water audits are complete, and ERCOT is scheduled to present its findings to the Public Utility Commission on December 10, 2026. New rules may follow from the PUC and the 2027 legislative session.

Why are so many data centers being built in Texas?

Land, a fast-growing grid, natural gas, a central location with good latency to both coasts and Mexico, and a regulatory culture used to large industrial projects.

What are the biggest AI data centers in Texas?

The Stargate campus in Abilene for OpenAI and Oracle, about 1.2 GW; Vantage's Frontier campus near Abilene, about 1.4 GW under construction; and planned projects including Fermi America near Amarillo and GW Ranch in Pecos County.

What is the Stargate data center in Abilene?

A campus built by Crusoe on the Lancium site in Abilene for OpenAI and Oracle, planned at about 1.2 GW. Buildings have been coming online since 2025, ramping through 2026.

What is happening with the Amarillo data center?

Fermi America's Project Matador near Amarillo was announced at up to about 11 GW, but construction paused in early 2026 and the project is delayed.

What is SB 6?

A 2025 Texas law setting rules for large loads of 75 MW and more on the ERCOT grid, including interconnection standards, financial security, disclosure of duplicate requests and curtailment readiness. Regulators are still finalizing parts of it.

Do the Texas pauses affect colocation?

Not for space in existing, energized buildings. They matter for new multi-megawatt and AI requirements that depend on new permits or interconnections, so confirm energization dates in writing.

Does Texas offer data center tax incentives?

Yes. Qualifying data centers of at least 100,000 square feet that meet investment and job thresholds can be exempt from state sales and use tax on qualifying equipment, and qualifying large projects of at least 250,000 square feet from local tax too. Texas has no state income tax. Both Governor Abbott and Governor-elect Hinojosa have called for ending data center incentives, so this may change in 2027.

How much does colocation cost in Texas?

Texas markets generally price below Northern Virginia and Chicago, with Dallas and San Antonio among the more affordable large markets. Quotes depend on power, cabinet count, term and connectivity.

Dallas or Houston for colocation?

Dallas for interconnection, the largest choice of buildings and wholesale capacity. Houston for proximity to energy and Gulf Coast companies. Many companies use one as a recovery site for the other, about 3.6 ms apart.

Is Texas a good place for AI and GPU colocation?

Yes for scale and liquid-cooled capacity, with the caveat that new power is slower after the 2026 pauses. Existing AI-ready halls in DFW and San Antonio are the fastest route.

Is the Texas grid reliable for data centers?

ERCOT set a preliminary demand record of 91,134 MW on July 22, 2026, and new rules require large loads to be ready to curtail in emergencies. Facilities rely on on-site generation and redundant feeds, which you should verify for any building.

Do you charge for finding Texas data center space?

No. The operator you choose pays us from its channel budget, and your rate is not marked up. You'll hear back within 24 hours.

Price Your Texas Requirement

Tell us power, cabinet or megawatt count, connectivity needs and date. You'll hear back within 24 hours from the person who will run your search. No cost, no obligation, and the operator you choose pays us.

Send it before you call an operator.
Once you have contacted an operator directly, it usually will not work through an advisor on your deal.
Price My Texas Requirement