Independent advisory for colocation, GPU and data center projects

A reply within one business day

Metro Colo Advisory research

Data Center Moratorium Tracker826 local and state actions that paused, banned, restricted or blocked data centers since January 2025, and 30 proposals still pending

Moratoriums, bans, zoning limits, state orders and blocked projects, town by town. Every row links to the agenda, ordinance, state record or news report behind it.

Explore the Map
Updated Nov. 21, 202646 states614 places with a measureEvery row linked to its sourceFree CSV under CC BY 4.0

A data center moratorium is a temporary pause on new data center applications, permits or construction, adopted by a town, county or state while officials study the effects and write permanent rules. Since January 2025 we count 856 local and state actions on data centers in 46 states: 493 moratoriums adopted and 77 extended, 67 bans, 67 zoning restrictions, 16 state actions, 106 project outcomes (denials, withdrawals, cancellations and pauses) and 30 votes still to come. Every row links to its source.

Actions tracked
856
local and state actions since January 2025, including 30 pending proposals
Places with a measure
614
towns, cities, townships, counties and states that adopted a moratorium, ban, zoning restriction or state action
Blocked or stalled projects
97
denied, withdrawn, canceled or paused, each project counted once
Stated investment
$136.9 billion
in those projects, counted once per project; only 18 of 97 state a figure
States covered
46
with at least one action in the tracker
Votes still to come
13
final votes scheduled after Nov. 21, 2026; 17 more proposals have no vote date yet

Data Center Moratoriums and Bans by State

Georgia has the most actions in the tracker, 85, followed by North Carolina (74) and Michigan (63). Darker states have more. Hover over or tap a state to see its breakdown, and click it to filter the table of every action below.

Actions per stateNone1 to 45 to 910 to 1920 to 3940 or more

Data Center Moratoriums Over Time

July 2026 had the most dated actions, 109. 714 of the dated actions came in 2026 through Nov. 21, against 78 in all of 2025. Each bar is one month, split into four groups.

Moratoriums and extensionsBans and zoning restrictionsBlocked projectsState actions

Source: Metro Colo Advisory Data Center Moratorium Tracker, data as of Nov. 21, 2026. Rows with a month but no day count in that month. 34 actions with no stated date, or only a year, are left out of this chart, as are the 30 pending proposals listed below. November 2026 runs through Nov. 21.

The Largest Blocked Data Center Projects

The largest blocked project by stated investment is Mooresville Technology Park in Town of Mooresville, Iredell County, North Carolina, at $30 billion. Together, the 18 blocked or stalled projects that state an investment add up to $136.9 billion.

$30 billionstated investment

Mooresville Technology Park

Town of Mooresville, Iredell County, North Carolina

Outcome
Withdrawn
Date
Aug. 13, 2025
Developer
Tract
Land
399 acres
Source: wsoctv.com
$24.7 billion2022 county staff estimate

Prince William Digital Gateway

Prince William County, Virginia

Outcome
Canceled
Date
July 2, 2026
Developer
QTS and Compass
Land
1,760 acres
Source: potomaclocal.com
$19.2 billionstated investment

Kingsboro AI data center

Edgecombe County (Kingsboro CSX Select Megasite), North Carolina

Outcome
Withdrawn
Date
July 6, 2026
Developer
Energy Storage Solutions (Daniel Shaffer)
Power
900 MW
Source: bisnow.com
$12 billionstated investment

DeForest data center

Village of DeForest, Dane County, Wisconsin

Outcome
Denied
Date
Feb. 3, 2026
Developer
QTS Data Centers
Land
1,572.5 acres
Source: engagedeforest.com
$10 billionstated investment

Prologis Leesburg data center campus

Kosciusko County (near Leesburg), Indiana

Outcome
Denied
Date
April 22, 2025
Developer
Prologis
Land
535 acres
Source: timesuniononline.com
$8.85 billionstated investment

Balico data center campus and gas plant

Pittsylvania County (near Chatham), Virginia

Outcome
Denied
Date
April 15, 2025
Developer
Balico
Land
750 acres
Source: cardinalnews.org
$6.4 billionstated investment

Proposed 50-acre data center

Town of Tarboro, Edgecombe County, North Carolina

Outcome
Denied
Date
Sept. 8, 2025
Developer
Energy Storage Solutions
Power
300 MW
Land
50 acres
Source: wral.com
$6 billionstated investment

Project Lincoln

Oldham County, Kentucky

Outcome
Withdrawn
Date
June 2, 2025
Developer
Western Hospitality Partners
Power
600 MW
Land
267 acres
Source: datacenterdynamics.com
Note

Most projects have no stated figure: 79 of the 97 blocked or stalled projects give no investment amount, so the $136.9 billion total is a floor. A project with two outcomes, such as a denial and then a withdrawal, is counted once, at its largest stated figure. Figures are as stated by the developer, a government body or in reporting, never estimated by us. The Prince William Digital Gateway figure is a 2022 county staff estimate for full buildout, not a developer figure.

Upcoming Data Center Moratorium Votes

13 votes are scheduled after Nov. 21, 2026, and the next is Bloomington, McLean County, Illinois on Nov. 23, 2026. 17 more are pending with no final vote date set yet. Soonest first.

  1. Nov. 23, 2026Bloomington City Council
    Bloomington, McLean County, IllinoisProposed 12-month extension of the city moratorium on hyperscale data centers, which expires at the end of November 2026wglt.org
  2. Nov. 23, 2026Chowan County Board of Commissioners
    Chowan County, North CarolinaTemporary moratorium on development approvals for data centers and related high-impact facilitieschowancounty-nc.gov
  3. Dec. 7, 2026Elkhart County Board of Commissioners
    Elkhart County, IndianaCounty data center zoning ordinance: siting away from homes and schools, setbacks, 7 a.m. to 7 p.m. noise hourswndu.com
  4. Dec. 8, 2026Broward County Board of County Commissioners
    Broward County, FloridaTemporary moratorium on large-scale data centers in unincorporated county (File 26-1486); first hearing Nov. 10, second hearing Dec. 8, 2026broward.legistar.com
  5. Dec. 8, 2026Hollis special town meeting (voters)
    Hollis, York County, MaineProposed town ordinance establishing a temporary moratorium on data centers, at a special town meetinghollismaine.org
  6. Dec. 8, 2026Whittier City Council
    Whittier, Los Angeles County, CaliforniaPossible extension of the 45-day data center moratorium by 10 months and 15 daysfoxla.com
  7. Dec. 15, 2026Gilbert Town Council
    Gilbert, Maricopa County, ArizonaProposed Land Development Code text amendment Z26-01: data centers only in light and general industrial zones with special permit; no potable water for cooling; no open-loop coolingkjzz.org
  8. Dec. 15, 2026Mandan voters (special election)
    Mandan, Morton County, North DakotaCitizen-initiated measure to prohibit large-scale data centers with 25 MW or more of electrical capacity or demand in Mandan and territory under city zoningcityofmandan.com
  9. Dec. 17, 2026Minneapolis City Council
    Minneapolis, Hennepin County, MinnesotaPermanent data center regulations (revised after the mayoral veto); planning commission hearing Dec. 14, 2026mprnews.org
  10. Dec. 21, 2026St. Cloud City Council
    St. Cloud, Stearns County, MinnesotaPossible one-year moratorium on new data centers (public hearing and possible vote)mprnews.org
  11. Jan. 12, 2027Brewer City Council
    Brewer, Penobscot County, MaineData center zoning regulations (water, electricity, noise, environment); would increase allowable size in industrial zones; not a banbrewermaine.gov
  12. Jan. 19, 2027Maricopa City Council
    Maricopa, Pinal County, ArizonaProposed zoning amendment establishing data center development standards: location, distance from homes, cooling and generator noise, water and electricity requirements, height and placement, designmaricopa-az.gov
  13. Feb. 23, 2027Fort Worth City Council
    Fort Worth, Tarrant County, TexasProposed 90-day moratorium on new data center development applications; excludes vested, approved and already-submitted zoning casesfortworthtexas.gov
  14. No final vote date set yet
  15. Date not setPima County Board of Supervisors
    Unincorporated Pima County, ArizonaZoning code text amendment: Type III conditional use permit with two hearings and supervisor approval, no open-loop cooling, written water and energy service guarantee, PFAS ban, larger setbacks, lower sound limits, generator and decommissioning ruleskold.com
  16. Date not setCromwell Planning and Zoning Commission
    Cromwell, Middlesex County, ConnecticutSix-month pause on new data center applicationswfsb.com
  17. Date not setEllington Planning and Zoning Commission
    Ellington, Tolland County, ConnecticutZ202615 regulation amendment: 12-month moratorium on battery energy storage systems and data centersresources.finalsite.net
  18. Date not setLake County Board of County Commissioners
    Lake County, FloridaProposed six-month extension of the pause on large-scale data center applications in unincorporated Lake County, through June 2027wftv.com
  19. Date not setBainbridge City Council
    City of Bainbridge, Decatur County, GeorgiaData center ordinance: data centers only in industrial zones, crypto mining banned, 20-acre minimum site, 1,000-ft separation from sensitive uses, noise caps, decommissioning securitythepostsearchlight.com
  20. Date not setDecatur County Board of Commissioners
    Decatur County, GeorgiaData center ordinance: data centers only in light and heavy industrial zones, crypto mining banned, 50-acre minimum site, 1,000-ft separation from homes, schools, churches; noise caps; decommissioning securitythepostsearchlight.com
  21. Date not setEffingham County Board of Commissioners
    Effingham County, GeorgiaProposed pause on certain future data center applicationswtoc.com
  22. Date not setSt. Joseph County Council
    St. Joseph County, IndianaZoning amendment prohibiting new hyperscale data centers in unincorporated St. Joseph Countywvpe.org
  23. Date not setBow Planning Board (then town vote)
    Bow, Merrimack County, New HampshirePetitioned ordinance pausing data center permitting and construction for at least a yearnhpr.org
  24. Date not setFayetteville City Council
    City of Fayetteville, Cumberland County, North CarolinaProposed 180-day moratorium on new or expanded data centerswebapi.legistar.com
  25. Date not setBuffalo Township Board of Supervisors
    Buffalo Township, Butler County, PennsylvaniaZoning amendment defining data centers and allowing them only as conditional uses in the M-2 manufacturing district, with site, utility, environmental impact and will-serve letter requirementsbutlereagle.com
  26. Date not setIndiana Township Board of Supervisors
    Indiana Township, Allegheny County, PennsylvaniaData center ordinance (contents not stated on notice)indianatownship.com
  27. Date not setBeaufort County Council
    Beaufort County, South CarolinaOrdinance 2026/55: 24-month moratorium on acceptance, processing and approval of data center applications and permits; passed first reading Nov. 9, 2026; two more readings neededbeaufortcosc.api.civicclerk.com
  28. Date not setShelby County Board of Commissioners
    Shelby County, Tennessee12-month moratorium on data centers in unincorporated county; passed first reading Oct. 12, 2026 (5-4); second and third readings pendingactionnews5.com
  29. Date not setDenton City Council
    Denton, Denton County, TexasProposed 90-day hold on new commercial data center development applications in the city, Denton Municipal Electric territory and city water and sewer territory; prior applications not affectedcommunityimpact.com
  30. Date not setLubbock City Council
    Lubbock, Lubbock County, TexasProposed 90-day moratorium on acceptance, processing or approval of rezoning, building permit and annexation applications for large-scale data centerskcbd.com
  31. Date not setLubbock City Council
    Lubbock, Lubbock County, TexasProposed zoning standards requiring specific zoning for large-scale data centers, with landscaping, setbacks, noise and pollution limits and decommissioningkcbd.com

Every Data Center Moratorium, Ban and Blocked Project

All 856 actions, newest first, each with its source. Search by place, project or developer, filter by state, action type or confidence, and tap a row for the governing body, the stated reason and a quote from the source.

Download CSV
DatePlaceActionScopeStatusConfidenceSource
Loading the table. Every action is also in the CSV download below.
Planning a data center site where a pause or a ban is on the table?We help developers and site owners read the local rules, the power path and the approval risk before they commit. You'll hear back within 24 hours.
Tell Us About Your Site

How We Built the Data Center Moratorium Tracker

Every row is one dated government action or one project outcome, and every row links to the record or report behind it.

What counts

  • Adopted measures only. A moratorium, ban, zoning restriction or state law, order or regulator decision counts once it passed a final vote, was signed or took effect, between Jan. 1, 2025 and Nov. 21, 2026. First readings, workshops and proposals do not.
  • Extensions are their own rows. When a place extends a moratorium, that vote is a new row (77 so far).
  • Pending proposals. A proposal is listed when its final vote is scheduled after Nov. 21, 2026 (13 rows), or when a hearing is set but no vote date is (17 rows). Neither is counted as adopted.
  • Project outcomes. A governing body denied a rezoning, permit or tax break; the developer withdrew or canceled; or the project was formally paused or delayed (tabled for 60 days or more, paused by the developer, or blocked in court). A project denied and then withdrawn has two rows but counts as one project.

Sources

Meeting agendas and minutes, adopted ordinance and resolution text, state legislature, governor and regulator records, court filings, local news, state public radio and trade press. 186 rows cite a government document as the main source, 658 cite news reports and 12 cite trade press. Every row carries a link, and most carry a short quote from the source showing the action.

We used other public trackers and lists to find leads, then went to the agenda, ordinance or news report behind each one. 23 rows still cite a tracker's briefing, as a second source or, in nine cases, the main source, where it reported the action; those rows are rated High, Medium or Low.

Confidence levels

181Higha government document: ordinance, minutes, agenda or state record
279Mediumtwo independent news reports
396Lowone news report

Known limits

  • 396 of 856 rows (46%) rest on a single local news report.
  • 80 rows have a month but no day, 2 have only a year and 49 have no stated date.
  • Coverage is still growing. Small towns and townships that post minutes late are the most likely to be missing, so counts are floors.
  • Investment, megawatt and acreage figures appear only where a source states them. We never estimate them.
  • To suggest an action or a correction, email contact@metrocoloadvisory.com.

For Reporters and Researchers

The full dataset is free to download and reuse under CC BY 4.0, with credit and a link to this page.

Download the data

All 856 actions with dates, scope, status, stated figures, sources, quotes and confidence. CSV, free to use.

Download CSV

How to cite

Metro Colo Advisory, "Data Center Moratorium Tracker," updated November 2026, https://metrocoloadvisory.com/data-center-moratoriums/. DOI: 10.5281/zenodo.24422321. License: CC BY 4.0.

Corrections

Spotted a missing vote, a wrong date or a moratorium that has ended? Email us the link and we will check it against the source.

contact@metrocoloadvisory.com

Free to use under a Creative Commons Attribution 4.0 license. Credit Metro Colo Advisory and link to this page.

Data Center Moratorium FAQ

Short answers, drawn from the tracker data as of Nov. 21, 2026.

What is a data center moratorium?

A data center moratorium is a temporary pause on new data center applications, permits or construction, adopted by a town, county or state while it studies the effects and writes permanent rules. Most run for a set term, often six months or a year, and many cover only large facilities or certain zones. Since January 2025 we count 493 moratoriums adopted and 77 extensions.

How many places have paused data centers?

495 towns, cities, townships and counties have adopted a data center moratorium since January 2025, by our count. Adding bans, zoning restrictions and state actions, 614 places in 45 states have adopted at least one measure that pauses or restricts data centers.

Which states have the most data center moratoriums?

Georgia leads with 66 moratoriums adopted or extended, followed by North Carolina (56), Michigan (53), Maine (34) and Ohio (34). Counting every type of action, including bans, blocked projects and pending votes, Georgia has the most, with 85.

Can a county ban data centers?

Often, yes. Counties that control zoning can pause new applications, limit data centers to certain zones or, in some places, prohibit them, but what a county may do depends on state law and on whether the land is inside a city or town. In our data, 195 counties adopted a moratorium, 14 adopted an outright ban or prohibition and 19 adopted zoning restrictions.

How long do data center moratoriums last?

Most run six months to a year. Of the 425 moratoriums whose term is stated, 181 set about one year and 132 about six months (often written as 180 days). 67 set less than six months, 5 set seven to eleven months and 40 set more than a year, up to 36 months. Many are renewed: we count 77 extensions.

What happens to data center projects during a moratorium?

Usually the town or county stops accepting or processing new applications until the pause ends, so early-stage projects wait or move elsewhere. Projects already approved, or covered by an earlier agreement, may be able to continue, depending on how the measure is written. Across all measures, we count 40 project denials, 48 withdrawals, 4 cancellations and 14 pauses or delays since January 2025.

How many data center projects have been blocked?

We count 97 data center projects that were denied, withdrawn, canceled or paused since January 2025. Only 18 of them state an investment figure, and those add up to $136.9 billion, counting each project once.

Where does the data come from?

From government records and reporting: meeting agendas and minutes, adopted ordinances and resolutions, state records and local news. 181 rows rest on a government document (high confidence), 279 on two independent news reports (medium) and 396 on one news report (low). Every row links to its source, and the full dataset is a free CSV download on this page.

Data as of Nov. 21, 2026. Part of Metro Colo Advisory Research.